EL25-49-000 · 2025-04-23 · Solar Energy Industries Association

Comments of Solar Energy Industries Association in response to FERC's 02/20/2025 Order Instituting Proceeding under Section 206 of the Federal Power Act et al

Text extracted from the eLibrary original (SHA-256 1b3238b058eac8f7…). Download the original from the official source.

Contents · 5 sections
  1. I. COMMENTS p. 3
  2. A. The Commission must base costs on grid use and should accommodate both p. 3
  3. B. The Commission should direct PJM to create processes in its Tariff to p. 5
  4. C. The Commission should direct PJM to fast-track new generation that would p. 9
  5. II. CONCLUSION p. 11

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

And each one of these stakeholders must work expeditiously to remove the barriers to that development and provide regulatory certainty.2 SEIA submits these comments in response to the Commission’s February 20, 2025 Order Instituting Proceeding under Section 206 of the Federal Power Act and…
Read this passage Filed comments: Connecting load and generation

I. COMMENTS

printed heading

I.
Read this passage

A. The Commission must base costs on grid use and should accommodate both

printed heading · Topic match: Cost allocation

The transmission and ancillary service costs must reflect the benefits the co-located load arrangement receives from the grid.7 The type of benefits received will depend on the specific co-location arrangement.8 As SEIA noted in our post-technical conference comments, some arrangements can be…
Read this passage Filed comments: Cost allocation

B. The Commission should direct PJM to create processes in its Tariff to

printed heading · Topic match: Connecting load and generation

Option 1, Load with a separate Point of Interconnection that is Network Load, explicitly provides that the load and generation are not co-located.20 Though presented as a large load co-location option for the Commission to consider,21 it does not meet PJM’s definition of co-located load because the…
Read this passage Filed comments: Connecting load and generation

C. The Commission should direct PJM to fast-track new generation that would

printed heading · Topic match: Connecting load and generation

Under this model, PJM would study the generator, whether utility owned or owned by an independent power producer, similar to how it would study surplus service requests, in order to determine whether any new Network Upgrades would be needed to facilitate the interconnection request.51 One…
Read this passage Filed comments: Connecting load and generation

II. CONCLUSION

printed heading · Topic match: Connecting load and generation

If the co-located interconnection study reveals that network upgrades are necessary, then the co-located interconnection request would be deemed ineligible for this interconnection service. 56 See PJM Surplus Filing at 5. 57 See Post-Technical Conference Comments of Buckeye Power, Inc. at 5-6,…
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

Dated the 23rd day of April, 2025. /s/ Melissa Alfano