EL25-49-000 · 2025-04-23 · Mainspring Energy

Comments of Mainspring Energy, Inc. on Co-located Generation and Data Center Integration

Text extracted from the eLibrary original (SHA-256 2bc9da713b955c94…). Download the original from the official source.

Contents · 2 sections
  1. Executive Summary p. 4
  2. Introduction p. 5

Read topic-matched comments in EL25-49

Topics in the text: Cost allocation · Reliability and curtailment · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

In the attached comments, Mainspring: ●​ Supports PJM’s exploration of new flexibility frameworks, including Options 6 and 7;​ ●​ Recommends preserving the two existing BTMG classes (retail and non-retail) while establishing a new tariff-defined class for repurposed legacy generation (Option 3);​…
Read this passage Filed comments: Cost allocation

Executive Summary

printed heading · Topic match: Cost allocation

This is a meaningful omission in the Tariff as many large generators are considering transitioning to this configuration to serve large loads. ●​ In addition, we also respectfully urge the Commission to preserve the existing and historic BTMG classes for resources that enter service behind a…
Read this passage Filed comments: Cost allocation

Introduction

printed heading · Topic match: Cost allocation

The following costs may be required when Generation Capacity Resources become Repurposed BTMG. ○​ Supplemental projects pursuant to local TO methodology ○​ RTEP upgrades pursuant to RTEP cost allocation ○​ Generator interconnection for the changes to its facility to accommodate the load Black Start…
Read this passage Filed comments: Cost allocation

CERTIFICATE OF SERVICE

printed heading

Dated at Merion Station, Pennsylvania this 23rd day of April, 2025. /s/ Brian Kauffman Brian Kauffman Director, Wholesale Market Development​ Mainspring Energy, Inc. 13
Read this passage