Comments of Electric Power Supply Association and the PJM Power Providers Group
Text extracted from the eLibrary original (SHA-256 36c9530baf2d80d8…). Download the original from the official source.
Contents · 8 sections
- Attachment H-1 to unilaterally designate any transmission service to co-located load is Network
- I. BACKGROUND
- II. COMMENTS
- A. Certain Restructured States in PJM Have Chosen to Unbundle and Not
- B. PJM’s Answer is Not Responsive to the Commission and Fails to
- C. The Transmission Owners’ Litigation Position is Anti-Competitive and
- D. The Commission Should Direct PJM to Convene a Time-Limited
- III. CONCLUSION
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Retail and wholesale authority
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
P3 filed a timely document-less Motion to Intervene in this proceeding on November 25, 2024. 2 Cause Order and answers submitted to that order on March 24, 2025, in particular the Answer of PJM Interconnection, L.L.C. (“PJM Answer”).5 EPSA and P3 agree with the Commission that PJM needs to…Read this passage Filed comments: Connecting load and generation
Attachment H-1 to unilaterally designate any transmission service to co-located load is Network
printed heading · Topic match: Cost allocation
The absence of such provisions may leave entities unable to determine what steps they can or must take to effectuate co-location arrangements of various configurations[.]”). 10 See Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures of the Electric…Read this passage Filed comments: Cost allocation
I. BACKGROUND
printed heading · Topic match: Connecting load and generation
BACKGROUND The Show Cause Order makes an initial finding that the PJM Open Access Transmission Tariff (“OATT”) appears to be unjust, unreasonable, and unduly discriminatory or preferential regarding rules to address co-location configurations between interconnected generators and co-located load…Read this passage Filed comments: Connecting load and generation
II. COMMENTS
printed heading
II.Read this passage
A. Certain Restructured States in PJM Have Chosen to Unbundle and Not
printed heading · Topic match: Retail and wholesale authority
Purporting to agree with the Commission’s nuanced statements in the Order, the Indicated PJM Transmission Owners aver that “[S]tate jurisdiction must be recognized and respected.Read this passage Filed comments: Retail and wholesale authority
B. PJM’s Answer is Not Responsive to the Commission and Fails to
printed heading · Topic match: Connecting load and generation
PJM’s rules must recognize that there are protective schemes that can shield the system from impacts of a large co-located load and, conversely, that can shield the co-located load from system disturbances.Read this passage Filed comments: Connecting load and generation
C. The Transmission Owners’ Litigation Position is Anti-Competitive and
printed heading · Topic match: Cost allocation
That must include assessing netting of charges in a non-discriminatory manner in order to reflect cost causation, for instance.Read this passage Filed comments: Cost allocation
D. The Commission Should Direct PJM to Convene a Time-Limited
printed heading
There are certain issues that must be prioritized to reach a just and reasonable Tariff.Read this passage
III. CONCLUSION
printed heading
CONCLUSION WHEREFORE, EPSA and P3 urge the Commission to consider the comments herein and establish a 90-day settlement process to allow PJM to work with stakeholders on the tariff provisions needed to address co-location arrangements sufficiently and fully.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 23rd day of April, 2025.Read this passage