Answer of PPL Electric Utilities Corporation to PJM Interconnection, L.L.C.'s et al. Answers
Text extracted from the eLibrary original (SHA-256 cc6017a6fb5279be…). Download the original from the official source.
Contents · 7 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Reliability and curtailment · Retail and wholesale authority
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. et al.Read this passage
I. INTRODUCTION
printed heading
INTRODUCTION The electric industry is now well into its second year of intense focus on large loads co- locating with wholesale generators.Read this passage
II. BACKGROUND
printed heading · Topic match: Connecting load and generation
Generators installing behind-the-meter load will have to reduce their capacity injection rights and load must have system protec- tions in place to protect the transmission system. • Non-network load cannot become network load without going through the various study processes.9 PPL Electric shared…Read this passage Filed comments: Connecting load and generation
III. ANSWER
printed heading
III.Read this passage
A. Responses to PJM
printed heading · Topic match: Connecting load and generation
Other transmission owners filed shorter responses without detailed substantive discussion of co-located load. 17 PJM Answer at 4. 7 As an initial matter, the PJM Answer accurately pinpoints the potential jurisdictional gaps that led to the situation at Susquehanna.18 Under prevailing Pennsylvania…Read this passage Filed comments: Connecting load and generation
B. Responses to PSEG
printed heading · Topic match: Retail and wholesale authority
Responses to PSEG PSE&G argues that the Commission should apply cost allocation rules developed in dis- putes between different transmission zones to the newly presented question of how transmission costs should be allocated among retail customers in a single transmission zone.43 It argues such a…Read this passage Filed comments: Retail and wholesale authority
C. Response to AES Ohio
printed heading · Topic match: Connecting load and generation
The PJM Tariff must accommo- date whatever choice the states make, but in doing so it must ensure (a) the safety and reliability of the transmission system is protected, and (b) that costs are not transferred from the behind the meter load to the network load.Read this passage Filed comments: Connecting load and generation
IV. CONCLUSION
printed heading · Topic match: Connecting load and generation
CONCLUSION For the reasons stated above and in the Comments of the Indicated PJM Transmission Owners, PPL Electric respectfully requests the Commission accept this Answer, find the existing PJM Tariff just and reasonable, and provide additional clarification regarding the treatment of…Read this passage Filed comments: Connecting load and generation
CERTIFICATE OF SERVICE
printed heading
Dated at Allentown, PA this 23rd day of April, 2025.Read this passage