EL25-49-000 · 2025-04-23 · Ohio Federal Energy Advocate

Comments of the Public Utilities Commission of Ohio's Office of the Federal Energy Advocate in response to FERC's 02/20/2025 Order

Text extracted from the eLibrary original (SHA-256 ee551975d39f9bcf…). Download the original from the official source.

Contents · 6 sections
  1. I. Background p. 1
  2. II. Comments p. 2
  3. A. Multiple Pathways Are Needed to Address Resource Adequacy Needs. p. 2
  4. B. Bring Your Own Generation (BYOG) Should Be Encouraged. p. 4
  5. C. Co-Located Load Must Pay for Grid Services Used. p. 5
  6. III. Conclusion p. 5

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. et al. ) Docket No.
Read this passage

I. Background

printed heading · Topic match: Connecting load and generation

Background The substantial grid challenges PJM is working to address are well known and a result of numerous simultaneous issues, including a changing generation resource mix, delayed capacity auctions, lengthy interconnection queue reform, and unprecedented forecasted load growth driven primarily…
Read this passage Filed comments: Connecting load and generation

II. Comments

printed heading

II.
Read this passage

A. Multiple Pathways Are Needed to Address Resource Adequacy Needs.

printed heading · Topic match: Reliability and curtailment

The Ohio FEA agrees that an “all hands on deck” approach is needed to meet supply and demand challenges in the region and appreciates PJM’s commitment “to facilitating and supporting co-location arrangements where permitted by applicable state law.”4 However, PJM must develop transparent processes…
Read this passage Filed comments: Reliability and curtailment

B. Bring Your Own Generation (BYOG) Should Be Encouraged.

printed heading · Topic match: Connecting load and generation

Under this option, various incentives could be explored, including faster processing of generation that enters the PJM interconnection queue to accommodate the co-located load.
Read this passage Filed comments: Connecting load and generation

C. Co-Located Load Must Pay for Grid Services Used.

printed heading · Topic match: Connecting load and generation

The Ohio FEA agrees with PJM that “participants involved in co-location arrangements should pay the costs of any grid services they consume and the arrangements must be reliable and operationally manageable.”8 Regardless of the co-located load configurations that may be approvable by the Commission…
Read this passage Filed comments: Connecting load and generation

III. Conclusion

printed heading · Topic match: Reliability and curtailment

Lindgren Assistant Attorney General Public Utilities Section 30 East Broad Street, 16th Floor Columbus, Ohio 43215-3414 614.644.8768 (telephone) 866.818.6152 (facsimile) Thomas.Lindgren@OhioAGO.gov On Behalf of the Public Utilities Commission of Ohio’s Office of the Federal Energy Advocate April…
Read this passage Filed comments: Reliability and curtailment

CERTIFICATE OF SERVICE

printed heading

Dated this the 23rd day of April 2025, at Columbus, Ohio. /s/ Thomas G.