Comments of the American Council on Renewable Energy on the 03/24/2025 Answer of PJM Interconnection, L.L.C
Text extracted from the eLibrary original (SHA-256 e4fb220239c983b8…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al.) Docket No.Read this passage
I. COMMENTS
printed heading
I.Read this passage
A. Further Guidance from the Commission is Warranted.
printed heading · Topic match: Cost allocation
ACORE supports PJM’s request “that the Commission issue detailed guiding principles such as those PJM proposes in this filing that PJM can promptly operationalize in a section 205 filing.”2 As described later in these comments, such guidance is especially warranted for Option 6 (Co-located load…Read this passage Filed comments: Cost allocation
B. Option 6 Requires Specific and Targeted Guidelines
printed heading · Topic match: Connecting load and generation
As noted above, any prioritization process must incorporate the timeline for the development of new resources.14 • Include additional guidelines for additional beneficial queue reforms to avoid overreliance on queue prioritizations, as was discussed extensively in the Commission’s September 2024…Read this passage Filed comments: Connecting load and generation
II. CONCLUSION
printed heading
CONCLUSION ACORE appreciates the careful consideration being given by the Commission and PJM to the need for clear policies on the co-location of large loads and generating resources.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated this 23th day of April, 2025. /s/ Elise Caplan Elise CaplanRead this passage