Joint Comments of PJM Industrial Customer Coalition and Industrial Energy Consumers of America
Text extracted from the eLibrary original (SHA-256 84d6a3152c7cdd41…). Download the original from the official source.
Contents · 7 sections
- I. BACKGROUND
- II. JOINT COMMENTS
- A. Billing For Commission-Jurisdictional Services Must Be Based on Actual Use
- B. The Indicated Transmission Owners Have Not Justified Discriminatory
- C. Adoption of a “Gross-Load” or “Potential Load” Approach Would
- D. Framing Co-Located Load as Getting a “Free Ride” Distorts the Impact of
- III. CONCLUSION
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket Nos.Read this passage
I. BACKGROUND
printed heading
BACKGROUND On February 20, 2025, the Commission unanimously voted to launch a review of issues associated with the co-location of large loads at generating facilities in PJM, including whether the PJM tariff needs to establish rules to create clarity while ensuring grid reliability.Read this passage
II. JOINT COMMENTS
printed heading
JOINT COMMENTS PJMICC and IECA are both coalitions representing industrial consumers in the PJM Region.Read this passage
A. Billing For Commission-Jurisdictional Services Must Be Based on Actual Use
printed heading · Topic match: Cost allocation
For decades, the Commission and the courts have understood this requirement to incorporate a ‘cost-causation principle’—the rates charged for electricity should reflect the costs of providing it.”) The Commission correctly states that the cost causation principle “provides that all…Read this passage Filed comments: Cost allocation
B. The Indicated Transmission Owners Have Not Justified Discriminatory
printed heading · Topic match: Connecting load and generation
Even further, the Indicated TOs do not explain why co-located load should be treated differently than BTMG customers, whose configurations are similar or identical to co-located load configurations.27 The Indicated TOs state in their Answer that “if a customer has the option, capability, or is…Read this passage Filed comments: Connecting load and generation
C. Adoption of a “Gross-Load” or “Potential Load” Approach Would
printed heading · Topic match: Connecting load and generation
The Indicated TOs state that “The transmission system must be planned and built to support every MW of load on the system, including co-located load.”35 The Indicated TOs do not explain how they would apply such a principle to peak load contribution (“PLC”) and network service peak load (“NSPL”)…Read this passage Filed comments: Connecting load and generation
D. Framing Co-Located Load as Getting a “Free Ride” Distorts the Impact of
printed heading · Topic match: Connecting load and generation
These 36 16 U.S.C. § 824s. 13 avoided costs are then subsidized by other customers, allowing co-location customers a free ride.”37 Further, the Indicated TOs state: As long as the load remains connected to the grid, including through facilities also connecting a generator to the grid, the load…Read this passage Filed comments: Connecting load and generation
III. CONCLUSION
printed heading
CONCLUSION WHEREFORE, the PJM Industrial Customer Coalition and the Industrial Energy Consumers of America respectfully request the Commission to consider these Comments supporting an approach to co-located loads aligned with actual use of the transmission system.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated this 23rd day of April, 2025. /s/ Matthew L.Read this passage