Comments of Data Center Coalition
Text extracted from the eLibrary original (SHA-256 8597bb9646c5ca18…). Download the original from the official source.
Contents · 9 sections
- I. COMMUNICATIONS
- II. INTRODUCTION
- II. REINFORCING DCC’S ESTABLISHED CO-LOCATION PRINCIPLES
- III. CLARIFYING THE NATURE OF CO-LOCATION
- IV. RESPONSE TO FERC’S SHOW CAUSE ORDER AND STAKEHOLDER POSITIONS
- V. RECOMMENDATIONS FOR IMPROVED LOAD FORECASTING
- VI. ENHANCED VISIBILITY INTO SUPPLEMENTAL PROJECTS AND REGIONAL LOAD
- VII. SPECIFIC RECOMMENDATIONS TO THE COMMISSION
- VIII. CONCLUSION AND SUMMARY OF KEY REQUESTS
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket Nos.Read this passage
I. COMMUNICATIONS
printed heading
COMMUNICATIONS Correspondence and communications regarding this filing should be directed to the following: Aaron Tinjum Vice President, Energy Data Center Coalition 525-K East Market Street #253 Leesburg, VA 20176 aaron@datacentercoalition.org Morgan A.Read this passage
II. INTRODUCTION
printed heading · Topic match: Connecting load and generation
In this context, co-location of load with generation—whether front-of-the-meter or behind-the- meter—is a pragmatic, common, and commercially legitimate strategy to secure timely access to power as markets grapple with years-long interconnection queue backlogs.Read this passage Filed comments: Connecting load and generation
II. REINFORCING DCC’S ESTABLISHED CO-LOCATION PRINCIPLES
printed heading · Topic match: Cost allocation
As the Commission considers whether and how to clarify the application of open access and cost allocation rules to these arrangements, it is critical that any resulting framework remain consistent with the following tenets: ● Preserving Open Access and Commercial Flexibility: Large Loads,…Read this passage Filed comments: Cost allocation
III. CLARIFYING THE NATURE OF CO-LOCATION
printed heading · Topic match: Connecting load and generation
The increased scrutiny of co-located load in the PJM footprint is not primarily about the nature of the arrangement itself.Read this passage Filed comments: Connecting load and generation
IV. RESPONSE TO FERC’S SHOW CAUSE ORDER AND STAKEHOLDER POSITIONS
printed heading · Topic match: Connecting load and generation
However, DCC emphasizes that these configurations must not only be acknowledged—they must be explicitly supported in PJM’s tariff to provide developers and large customers with the certainty necessary to proceed with time-sensitive projects.Read this passage Filed comments: Connecting load and generation
V. RECOMMENDATIONS FOR IMPROVED LOAD FORECASTING
printed heading · Topic match: Reliability and curtailment
While no forecast will ever be perfect, the Commission must take steps to modernize load forecasting practices across all levels of the system and hold PJM accountable for ensuring its forecasts reflect the best available data and methods.Read this passage Filed comments: Reliability and curtailment
VI. ENHANCED VISIBILITY INTO SUPPLEMENTAL PROJECTS AND REGIONAL LOAD
printed heading · Topic match: Reliability and curtailment
These modest improvements would help ensure that infrastructure decisions made at the local level are visible within broader planning discussions and appropriately reflected in resource adequacy and transmission assessments.Read this passage Filed comments: Reliability and curtailment
VII. SPECIFIC RECOMMENDATIONS TO THE COMMISSION
printed heading · Topic match: Cost allocation
SPECIFIC RECOMMENDATIONS TO THE COMMISSION In light of the issues raised in this proceeding and the recommendations outlined in the sections above, the Data Center Coalition respectfully urges the Commission to take the following actions to support a durable, transparent, and flexible framework for…Read this passage Filed comments: Cost allocation
VIII. CONCLUSION AND SUMMARY OF KEY REQUESTS
printed heading · Topic match: Connecting load and generation
CONCLUSION AND SUMMARY OF KEY REQUESTS The issues raised in this proceeding lie at the intersection of rapidly evolving load growth, strained infrastructure, and regulatory frameworks that must adapt to new market realities.Read this passage Filed comments: Connecting load and generation
CERTIFICATE OF SERVICE
printed heading
Dated at Herndon, VA this 23 day of April 2025. /s/ Morgan A.Read this passage