EL25-49-000 · 2025-04-23 · Johns Hopkins University

Comments of Suzanne Glatz and Abraham Silverman in response to PJM Interconnection, L.L.C.'s et al. 03/24/2025 filings

Text extracted from the eLibrary original (SHA-256 1ddc8c4dde37ee72…). Download the original from the official source.

Contents · 12 sections
  1. I. Summary p. 1
  2. II. Background of Suzanne Glatz and Abraham Silverman p. 3
  3. III. Comments p. 4
  4. A. PJM’s Existing NITS Rules are Just and Reasonable and Not Unduly p. 4
  5. B. Any Just and Reasonable Changes to PJM’s Tariff Should Ensure that p. 5
  6. C. Principles for a New Interconnection Service if FERC Determines that p. 6
  7. D. The Need for a Co-Location “Safety Valve” to Ensure System Reliability and p. 9
  8. E. The Commission Should Address the Risk of Stranded Transmission p. 11
  9. F. The Commission Should Take PJM Up on its Offer to Develop a Non-Firm p. 12
  10. G. The Commission Should Clarify the Regulatory Obligations of Generators p. 13
  11. H. The Commission Should Ensure that any Proposed Changes go Through a p. 15
  12. IV. Conclusion p. 15

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket Nos.
Read this passage

I. Summary

printed heading · Topic match: Reliability and curtailment

Whether load is co-located with generation in a “behind-the-generator-meter” configuration or in a conventional load connection, the issue remains that PJM must balance the amount of new data center load and new generation resources for the system to remain reliable and affordable.
Read this passage Filed comments: Reliability and curtailment

II. Background of Suzanne Glatz and Abraham Silverman

printed heading

Background of Suzanne Glatz and Abraham Silverman These comments are submitted on behalf of Suzanne Glatz and Abraham Silverman.
Read this passage

III. Comments

printed heading

III.
Read this passage

A. PJM’s Existing NITS Rules are Just and Reasonable and Not Unduly

printed heading · Topic match: Reliability and curtailment

While existing rules also allow utilities to ensure that new loads are connected in an orderly manner and that new service is only allowed to commence once transmission needs have been addressed, any accelerated co-location process must address what happens if a co-location request would…
Read this passage Filed comments: Reliability and curtailment

B. Any Just and Reasonable Changes to PJM’s Tariff Should Ensure that

printed heading · Topic match: Cost allocation

If the Commission elects to direct changes to PJM’s existing tariff methodology for assigning transmission charges to co-located load, it should ensure that use-cases with similar electrical impacts pay comparable rates.
Read this passage Filed comments: Cost allocation

C. Principles for a New Interconnection Service if FERC Determines that

printed heading · Topic match: Connecting load and generation

When CIRs are removed from the system, the existing load must still be served and the generation to serve that load may require new network upgrades.
Read this passage Filed comments: Connecting load and generation

D. The Need for a Co-Location “Safety Valve” to Ensure System Reliability and

printed heading · Topic match: Reliability and curtailment

The Show Cause Order asked the parties to “explain whether the existing Tariff rules are sufficient to ensure resource adequacy if increasing numbers of large existing generators 10 choose to co-locate with load.”15 In our view, the mass migration of existing generators to a co-location…
Read this passage Filed comments: Reliability and curtailment

E. The Commission Should Address the Risk of Stranded Transmission

printed heading · Topic match: Cost allocation

The stranded cost risk to consumers is real, particularly as virtually 12 all of PJM’s proposed solutions continue to have data center-driven transmission investments collected through socialized cost allocation methodologies that are often spread costs over multiple jurisdictions.
Read this passage Filed comments: Cost allocation

F. The Commission Should Take PJM Up on its Offer to Develop a Non-Firm

printed heading

The Commission Should Take PJM Up on its Offer to Develop a Non-Firm or Interruptible Tariff for Co-Located Resources.
Read this passage

G. The Commission Should Clarify the Regulatory Obligations of Generators

printed heading · Topic match: Reliability and curtailment

“No Party shall permit its Transmission Facilities or distribution facilities to be connected with the facilities of any entity which is not a Party without an interconnection agreement that contains provisions for the safe and reliable operation of each interconnection in accordance with Good…
Read this passage Filed comments: Reliability and curtailment

H. The Commission Should Ensure that any Proposed Changes go Through a

printed heading

The Commission Should Ensure that any Proposed Changes go Through a Thorough Stakeholder Vetting.
Read this passage

IV. Conclusion

printed heading

Conclusion The current PJM Tariff process for connecting network load or point-to-point load is just and reasonable as it currently exists.
Read this passage