Motion to Intervene and Comments of the Electricity Consumers Resource Council to PJM Interconnection, L.L.C. 's Answer to the Section 206 Show Cause Order
Text extracted from the eLibrary original (SHA-256 f3048055aa333e26…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in EL25-49
Topics in the text: Cost allocation · Connecting load and generation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) PJM Interconnection, L.L.C. et al. ) Docket No.Read this passage
SUMMARY
printed heading · Topic match: Connecting load and generation
In addition, as explained below, while resolving co-location concerns is important, more attention must be paid to the broader load forecasting and planning issues that are implicated by this current period of exponential load growth.Read this passage Filed comments: Connecting load and generation
A. The Commission Should Clarify Jurisdictional Boundaries Around Co-
printed heading · Topic match: Retail and wholesale authority
Large load customers may consider entirely “islanded” configurations that are not contemplated in this docket and may fall under state jurisdiction rather than federal jurisdiction.Read this passage Filed comments: Retail and wholesale authority
B. Cost Allocation Policies Should Adhere to the Core Principles of “Cost
printed heading · Topic match: Cost allocation
Cost Allocation Policies Should Adhere to the Core Principles of “Cost Causation” and “Beneficiary Pays” The economic principles of cost causation and beneficiary pays ensure equitable and fair allocation of grid costs so that one customer class does not subsidize the other.Read this passage Filed comments: Cost allocation
C. The Commission Should Give Greater Attention to Broader Load
printed heading
The Commission Should Give Greater Attention to Broader Load Forecasting and Planning Issues Implicated by Exponential Load Growth As referenced above, co-location is just one tool to serve immediate operational needs while more fundamental challenges with interconnection, transmission development,…Read this passage
CONCLUSION
printed heading · Topic match: Cost allocation
The Commission has the opportunity to clarify jurisdictional authorities surrounding co-location arrangements, develop a cost allocation framework that supports the efficient and equitable development of electric generation co-location, while safeguarding the reliability of the electric grid and…Read this passage Filed comments: Cost allocation
CERTIFICATE OF SERVICE
printed heading
Dated the 23rd day of April 2025. /s/ Karen Onaran Karen Onaran President & CEO Electricity Consumers Resource Council 700 12th Street, NW, Suite 700 Washington, DC 20005 KOnaran@elcon.orgRead this passage