EL25-49-000 · 2025-04-23 · Monitoring Analytics, LLC

Comments of the Independent Market Monitor for PJM

Text extracted from the eLibrary original (SHA-256 732b8e6e6bc5f430…). Download the original from the official source.

Contents · 11 sections
  1. I. COMMENTS p. 2
  2. A. Option 1: Load with a separate Point of Interconnection that is Network Load p. 9
  3. B. Option 2: Co-located load that is at the same Point of Interconnection but p. 10
  4. C. Option 3: Existing Behind the Meter Generation where the load is the customer p. 10
  5. D. Option 4: Co-located load with connection to the grid with protections to avoid p. 10
  6. E. Option 5: Co-located load with connection to the grid with protections to avoid p. 10
  7. F. Option 6: Co-located load that elects to be Network Load and bring its own p. 11
  8. G. Option 7: Potential new non-capacity backed service as a Transitional Service p. 11
  9. H. Option 8: Co-located load participating in Demand Response p. 12
  10. I. Jurisdictional Issues p. 13
  11. II. CONCLUSION p. 14

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

EL25-49-000 COMMENTS OF THE INDEPENDENT MARKET MONITOR FOR PJM Pursuant to Rule 211 of the Commission’s Rules and Regulations,1 Monitoring Analytics, LLC, acting in its capacity as the Independent Market Monitor (“Market Monitor”) for PJM Interconnection, L.L.C. (“PJM”),2 submits these comments…
Read this passage Filed comments: Connecting load and generation

I. COMMENTS

printed heading · Topic match: Connecting load and generation

PJM has proposed an extremely high maximum price in the capacity market and proposes even higher maximum prices.5 These prices are relevant when the market is clearing at the maximum price.
Read this passage Filed comments: Connecting load and generation

A. Option 1: Load with a separate Point of Interconnection that is Network Load

printed heading

Option 1: Load with a separate Point of Interconnection that is Network Load The Market Monitor supports this option as part of Option 6 for the reasons detailed in this filing.
Read this passage

B. Option 2: Co-located load that is at the same Point of Interconnection but

printed heading · Topic match: Connecting load and generation

Option 2: Co-located load that is at the same Point of Interconnection but separately metered that is Network Load The Market Monitor supports this option as part of Option 6 for the reasons detailed in this filing.
Read this passage Filed comments: Connecting load and generation

C. Option 3: Existing Behind the Meter Generation where the load is the customer

printed heading

Option 3: Existing Behind the Meter Generation where the load is the customer The Market Monitor opposes the use of this option for large loads.
Read this passage

D. Option 4: Co-located load with connection to the grid with protections to avoid

printed heading · Topic match: Connecting load and generation

Option 4: Co-located load with connection to the grid with protections to avoid delivery of system energy to serve the load The Market Monitor opposes this option for the reasons detailed in this filing.
Read this passage Filed comments: Connecting load and generation

E. Option 5: Co-located load with connection to the grid with protections to avoid

printed heading · Topic match: Connecting load and generation

Option 5: Co-located load with connection to the grid with protections to avoid delivery of system energy to load, but with back-up service from PJM with permission The Market Monitor opposes this option for the reasons detailed in this filing.
Read this passage Filed comments: Connecting load and generation

F. Option 6: Co-located load that elects to be Network Load and bring its own

printed heading · Topic match: Connecting load and generation

Option 6: Co-located load that elects to be Network Load and bring its own generation The Market Monitor supports this option with the proviso that the load is connected to the grid directly rather than in the narrow sense of co-location as defined, for the reasons detailed in this filing.
Read this passage Filed comments: Connecting load and generation

G. Option 7: Potential new non-capacity backed service as a Transitional Service

printed heading · Topic match: Connecting load and generation

The recent filing of a Necessary Study Agreement (NSA) by PJM and Doswell Generation illustrates many of the issues with this approach.8 Most significantly, the NSA proposes that the generating unit retain its CIRs during the transition, which is of uncertain duration.
Read this passage Filed comments: Connecting load and generation

H. Option 8: Co-located load participating in Demand Response

printed heading · Topic match: Connecting load and generation

Option 8: Co-located load participating in Demand Response The Market Monitor opposes this option for the reasons detailed in this filing and for the reasons in the response to Option 7.
Read this passage Filed comments: Connecting load and generation

I. Jurisdictional Issues

printed heading · Topic match: Connecting load and generation

Jurisdictional Issues The Show Cause Order provides guidance on jurisdictional issues related to co- location and requests comment (at P 73).
Read this passage Filed comments: Connecting load and generation

II. CONCLUSION

printed heading

CONCLUSION The Market Monitor respectfully requests that the Commission afford due consideration to these comments as it resolves the issues raised in this proceeding.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Eagleville, Pennsylvania, this 23rd day of April, 2025.