Response of Advanced Energy United to PJM Interconnection, L.L.C.’s Answer to the Show Cause Order
Text extracted from the eLibrary original (SHA-256 6c00247cb31a832b…). Download the original from the official source.
Contents · 10 sections
- I. EXECUTIVE SUMMARY
- II. COLOCATION AND THE BROADER ENERGY LANDSCAPE
- III. PERSPECTIVES ON CO-LOCATION ISSUES
- A. The Commission Should Act Within its Jurisdiction to Facilitate Fair Co-
- B. PJM Tariffs Regarding Co-Location Agreements Do Not Provide Sufficient
- C. Transmission, Ancillary, and Other Wholesale Service Charges for Co-Location
- D. Interconnection Procedures and Cost Allocation Must be Adapted and Clarified,
- E. PJM Should Enhance its Planning and Load Forecasting Processes to More
- F. Other Considerations
- IV. CONCLUSION
Read topic-matched comments in EL25-49
Topics in the text: Reliability and curtailment · Connecting load and generation · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. et al.Read this passage
I. EXECUTIVE SUMMARY
printed heading · Topic match: Reliability and curtailment
After initially resolving some of the key questions regarding co-location in the PJM region and gathering pertinent information from the Commissioner-led Technical Conference on Meeting the Challenge of Resource Adequacy,8 FERC could issue broad guidance but require each transmission provider to…Read this passage Filed comments: Reliability and curtailment
II. COLOCATION AND THE BROADER ENERGY LANDSCAPE
printed heading · Topic match: Reliability and curtailment
The Commission must continue to focus on the larger issues causing resource adequacy shortages across the country, including through the upcoming Resource Adequacy Technical Conference.18 Nevertheless, within this broader context of ongoing regulatory reforms and rapid load growth, co-location…Read this passage Filed comments: Reliability and curtailment
III. PERSPECTIVES ON CO-LOCATION ISSUES
printed heading
III.Read this passage
A. The Commission Should Act Within its Jurisdiction to Facilitate Fair Co-
printed heading · Topic match: Connecting load and generation
Solutions to these issues must be weighed against state policies and goals pertaining to economic development, generation mix, energy affordability, and other priorities.Read this passage Filed comments: Connecting load and generation
B. PJM Tariffs Regarding Co-Location Agreements Do Not Provide Sufficient
printed heading · Topic match: Connecting load and generation
Developing these options proactively and generically—but with sufficient flexibility to accommodate individual circumstances and evolution of co-location opportunities—before more individual requests come before PJM and the Commission would not only provide clarity for large loads and generation,…Read this passage Filed comments: Connecting load and generation
C. Transmission, Ancillary, and Other Wholesale Service Charges for Co-Location
printed heading · Topic match: Cost allocation
PJM does recognize that some Options (i.e., Options 4 and 5) may avoid some network charges, but does not define how a “new rate design” would be developed, nor how flexible it 46 PJM Answer at 38 47 “FERC must ensure that rates are just and reasonable and not unduly discriminatory, which requires…Read this passage Filed comments: Cost allocation
D. Interconnection Procedures and Cost Allocation Must be Adapted and Clarified,
printed heading · Topic match: Connecting load and generation
Interconnection Procedures and Cost Allocation Must be Adapted and Clarified, Especially to Expedite New Generation Under BYOG Loads and generators pursuing co-location arrangements need clarity as to how these arrangements will be studied, and how those studies will be evaluated.Read this passage Filed comments: Connecting load and generation
E. PJM Should Enhance its Planning and Load Forecasting Processes to More
printed heading · Topic match: Reliability and curtailment
AD24-11, Transcript at 28. 57 Post-Conference Comments of the Clean Energy Buyers Alliance in AD24-11, at 13-15; Post-Conference Comments of Google LLC in AD24-11, at 7-8. 24 Further, PJM must align its internal M3 Supplemental process for load interconnections with its annual load forecast, which…Read this passage Filed comments: Reliability and curtailment
F. Other Considerations
printed heading · Topic match: Reliability and curtailment
Any tariff changes PJM must make, while increasing standardization of the process, must 25 also allow for maximum flexibility to allow for new technologies.Read this passage Filed comments: Reliability and curtailment
IV. CONCLUSION
printed heading
CONCLUSION For the reasons above, Advanced Energy United respectfully requests that the Commission consider these comments and rule expeditiously to reduce regulatory uncertainty and allow large loads and new generation to enter the markets.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, DC this 23rd day of April, 2025. /s/ Mike HaughRead this passage