EL25-49-000 · 2025-04-23 · Natural Resources Defense Council

Comments of Natural Resources Defense Council in response to FERC's 02/20/2025 Order and PJM Interconnection, L.L.C.'s 03/24/2025 Answer

Text extracted from the eLibrary original (SHA-256 5ad73a6c1fc554ff…). Download the original from the official source.

Contents · 6 sections
  1. I. INTRODUCTION p. 2
  2. II. COMMENTS p. 2
  3. A. Co-Located Load Remains Retail Load and is Unambiguously Under State p. 2
  4. B. Certain Proposals in the PJM Answer Would Result in Unduly Preferential p. 3
  5. C. The PJM Answer Fails to Address Important Planning and Reliability Issues p. 7
  6. III. CONCLUSION p. 10

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Cost allocation · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) PJM Interconnection, L.L.C. et. al. ) Docket Nos.
Read this passage

I. INTRODUCTION

printed heading · Topic match: Cost allocation

However, in some areas PJM’s Answer appears to suggest unduly preferential treatment for co-located loads or their associated generation, and the Answer also misses several specific issues that if left unaddressed could lead to unjust cost shifting or reliability violations.
Read this passage Filed comments: Cost allocation

II. COMMENTS

printed heading

II.
Read this passage

A. Co-Located Load Remains Retail Load and is Unambiguously Under State

printed heading · Topic match: Connecting load and generation

Co-Located Load Remains Retail Load and is Unambiguously Under State Jurisdiction We join OPSI in requesting the Commission affirm that the sale between co-located load and the generator is a retail sale subject to state jurisdiction.4 We agree with the Commission’s statement in the Order that:…
Read this passage Filed comments: Connecting load and generation

B. Certain Proposals in the PJM Answer Would Result in Unduly Preferential

printed heading · Topic match: Connecting load and generation

The PJM Answer proposes one option in which co-located load elects to be network load and bring its own generation—either in the form of new generation or arrangements with existing generation that has or is scheduled to deactivate.
Read this passage Filed comments: Connecting load and generation

C. The PJM Answer Fails to Address Important Planning and Reliability Issues

printed heading · Topic match: Cost allocation

To maintain reliability, capacity must be procured for any significant load with the possibility of withdrawing from PJM’s grid during emergencies, such as would occur for a co-located load if the associated generator fails.
Read this passage Filed comments: Cost allocation

III. CONCLUSION

printed heading

CONCLUSION NRDC respectfully requests the Commission consider these comments in determining what reforms to PJM rules are necessary to accommodate co-location and large loads.
Read this passage

CERTIFICATE OF SERVICE

printed heading

CERTIFICATE OF SERVICE I hereby certify that the foregoing has been or soon will be served in accordance with 18 C.F.R. § 385.2010 upon each party designated in the official service list compiled by the Secretary in this proceeding, by email. /s/ Thomas Rutigliano Thomas Rutigliano Senior Advocate,…