Answer of PJM Interconnection, L.L.C. to Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures
Text extracted from the eLibrary original (SHA-256 93f05372a51713b1…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Filing procedure · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.Read this passage
I. PJM’S TARIFF REMAINS JUST AND REASONABLE
printed heading
PJM’S TARIFF REMAINS JUST AND REASONABLE Contrary to the Motion’s conclusory assertions, the ever-growing record in this proceeding reflects substantial support for a finding that PJM’s existing Tariff is just and reasonable in regards to co-location arrangements.3 As noted, PJM intends to submit a…Read this passage
II. NO STAY SHOULD ISSUE
printed heading · Topic match: Connecting load and generation
EL25-49, et al. (April 23, 2025). 4 movants now seeking a stay filed a co-located load-related complaint requesting fast track processing.4 When PJM filed a motion to extend the answer deadline, that request was firmly opposed – with one of the Motion’s sponsors then claiming “‘justice delayed is…Read this passage Filed comments: Connecting load and generation
III. PJM COMMENTS ON THE REQUEST FOR SETTLEMENT JUDGE
printed heading · Topic match: Reliability and curtailment
AD24-11. 11 See FERC News Release. 6 generally, including at an upcoming May 9, 2025 Large Load Additions workshop,12 as well as interrelated efforts pertaining to load forecasting and resource adequacy.Read this passage Filed comments: Reliability and curtailment
IV. CONCLUSION
printed heading
CONCLUSION PJM requests that the Commission consider this Answer when deciding the Motion.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Audubon, Pennsylvania, this 5th day of May 2025. /s/ Mark J.Read this passage