Motion for Expedited Action of Constellation Energy Generation, LLC re PJM Interconnection, L.L.C.’s Open Access Transmission Tariff et al
Text extracted from the eLibrary original (SHA-256 c7542f7412e88c3c…). Download the original from the official source.
Contents · 7 sections
- EXECUTIVE SUMMARY
- I. Constellation Supports the ANOPR’s Fourteen Principles with Limited Qualifications
- II. The Commission Should Find the Existing PJM Tariff Unjust and Unreasonable and
- A. The Commission Should Immediately Issue a Full Order on the Merits in the
- B. Alternatively, the Commission Should Immediately Issue a Targeted Order in the
- CONCLUSION
- Summary
Read topic-matched comments in EL25-49
Topics in the text: Reliability and curtailment · Connecting load and generation · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
Specifically, Constellation respectfully requests that the Commission immediately issue a full order on the merits in this show cause proceeding that (i) adopts the Commission’s preliminary finding that PJM Interconnection, L.L.C.’s Open Access Transmission Tariff is unjust and unreasonable and…Read this passage Filed comments: Connecting load and generation
CERTIFICATE OF SERVICE
printed heading
RM26-4-000 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Interconnection of Large Loads to the Interstate Transmission System PJM Interconnection, L.L.C., et al.Read this passage
EXECUTIVE SUMMARY
printed heading · Topic match: Reliability and curtailment
The current load interconnection process in PJM in practice cedes control of all large load interconnections to the discretion of Transmission Owners, regardless of the facilities to which the load proposes to interconnect.Read this passage Filed comments: Reliability and curtailment
I. Constellation Supports the ANOPR’s Fourteen Principles with Limited Qualifications
printed heading · Topic match: Connecting load and generation
Ming testified that net charges were appropriate (rather than gross), but also discussed a potential “standby charge” since “there is a high likelihood that the co-located generator will be available during the coincident peak hours, meaning that the co-located load is unlikely to be withdrawing…Read this passage Filed comments: Connecting load and generation
II. The Commission Should Find the Existing PJM Tariff Unjust and Unreasonable and
printed heading
The Commission Should Find the Existing PJM Tariff Unjust and Unreasonable and Provide Immediate ReliefRead this passage
A. The Commission Should Immediately Issue a Full Order on the Merits in the
printed heading · Topic match: Reliability and curtailment
See Constellation’s May 8, 2025 Preliminary Finding Answer at 14. 137 Constellation’s April 23, 2025 Show Cause Answer at 6, 52-55; see also Constellation’s May 8, 2025 Preliminary Finding Answer at 14-15. 138 Constellation’s April 23, 2025 Show Cause Answer at 52-55. 139 Id. at 71-73; see also…Read this passage Filed comments: Reliability and curtailment
B. Alternatively, the Commission Should Immediately Issue a Targeted Order in the
printed heading
The Commission Should Require PJM and Transmission Owners to Immediately Act on Large Load Studies and Interconnections The ANOPR’s central objective is “to ensure the timely and orderly interconnection of large loads.”147 Accordingly, the Commission should order Transmission Owners to timely…Read this passage
CONCLUSION
printed heading · Topic match: Credit and exit
CONCLUSION WHEREFORE, Constellation requests that the Commission propose and implement a final large load interconnection rule consistent with the Secretary of Energy’s fourteen principles, as qualified herein, by April 30, 2026.Read this passage