EL25-49-000 · 2025-12-05 · Constellation Energy Generation, LLC

Motion to File Supplemental Comments of Constellation Energy Generation, LLC

Text extracted from the eLibrary original (SHA-256 7d3b43d3177bcdbe…). Download the original from the official source.

Contents · 17 sections
  1. I. There Is Broad Consensus in the Record for How the Commission Should Act p. 9
  2. A. The Commission Should Act Quickly p. 9
  3. B. The Commission Should Act on Record Evidence of Undue Preference, Undue p. 11
  4. C. The Commission Should Accommodate Regional Differences p. 16
  5. D. The Commission Should Avoid Unnecessary Jurisdictional Fights p. 17
  6. II. Constellation Continues to Support the ANOPR’s Principles with Qualifications p. 18
  7. CONCLUSION p. 44
  8. I. QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT p. 47
  9. A. QUALIFICATIONS p. 47
  10. B. BACKGROUND AND PURPOSE OF AFFIDAVIT p. 47
  11. II. PURPOSE AND OPERATION OF THE ENHANCED BACKSTOP p. 48
  12. C. CERTAIN DESIGN FEATURES OF THE RPM POTENTIALLY LIMIT p. 48
  13. D. THE ENHANCED BACKSTOP WORKS WITHIN THE STRUCTURE OF THE p. 50
  14. III. THE ENHANCED BACKSTOP WILL INCREASE CONFIDENCE IN PJM MARKETS WHILE p. 54
  15. E. THE ENHANCED RELIABILITY BACKSTOP WILL ALLOW PJM MARKETS p. 54
  16. F. THE ENHANCED BACKSTOP HAS BEEN CAREFULLY DESIGNED TO p. 55
  17. IV. CERTAIN FEATURES OF THE ENHANCED BACKSTOP COULD BE VARIED TO ACHIEVE A p. 58

Read topic-matched comments in EL25-49

Topics in the text: Reliability and curtailment · Connecting load and generation · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword. Pages with no text layer: 62.

Opening text

opening text

Department of Energy, Secretary of Energy, Letter to FERC re: “Ensuring the Timely and Orderly Interconnection of Large Loads,” Advance Notice of Proposed Rulemaking (Oct. 23, 2025) (issued pursuant to Department of Energy Organization Act § 403, 42 U.S.C. § 7173) (cover letter, “Secretary’s…
Read this passage

CERTIFICATE OF SERVICE

printed heading · Topic match: Reliability and curtailment

Commissioners and key parties also support prompt guidance in PJM, and an order there can capitalize on consensus in the ANOPR record.3 On jurisdiction, the only immediate call the Commission must make in PJM is whether to exercise jurisdiction over hybrid facilities’ shared point of…
Read this passage Filed comments: Reliability and curtailment

I. There Is Broad Consensus in the Record for How the Commission Should Act

printed heading

There Is Broad Consensus in the Record for How the Commission Should Act Four areas of consensus emerge from the initial comments and should guide the Commission’s next steps on large load interconnection reform.
Read this passage

A. The Commission Should Act Quickly

printed heading · Topic match: Retail and wholesale authority

While FERC is considering urgent short-term fixes, it also must evaluate longer-term solutions that shape the sector.”). 6 clarity and finality.”13 Certain states and the minority of parties that urge delay largely are concerned about federal-state jurisdiction and disruption to ongoing state and…
Read this passage Filed comments: Retail and wholesale authority

B. The Commission Should Act on Record Evidence of Undue Preference, Undue

printed heading · Topic match: Connecting load and generation

See Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, Constellation Energy 9 order rejecting the Susquehanna Nuclear amended Interconnection Service Agreement (“ISA”) cemented the Transmission Owners’ refusal to process certain large load requests – effectively…
Read this passage Filed comments: Connecting load and generation

C. The Commission Should Accommodate Regional Differences

printed heading · Topic match: Registry access

EL25- 20-000, et al., at 8 (filed Nov. 22, 2024) (“Co-locating a new large load with a generator results in faster service on different terms but such projects are being held hostage by a few monopolies refusing to cooperate with reliability studies related to interconnection modifications.”). 30…
Read this passage Filed comments: Registry access

D. The Commission Should Avoid Unnecessary Jurisdictional Fights

printed heading · Topic match: Registry access

The Commission Should Avoid Unnecessary Jurisdictional Fights A fourth area of consensus is that the Commission should avoid unnecessary jurisdictional fights in any national rule because a “jurisdictional dispute over load interconnection would be counterproductive.”31 In Constellation’s view, the…
Read this passage Filed comments: Registry access

II. Constellation Continues to Support the ANOPR’s Principles with Qualifications

printed heading · Topic match: Reliability and curtailment

While Constellation is supportive of the concept of TSAs to deter speculative load interconnection requests, it is important that those TSAs contain some component reflective of upgrade costs (to create an incentive to locate most efficiently), and that they do not discourage legitimate projects by…
Read this passage Filed comments: Reliability and curtailment

CONCLUSION

printed heading

CONCLUSION WHEREFORE, Constellation respectfully requests that the Commission issue an order on the merits in PJM139 by the end of the year and a NOPR by the end of the year or as soon as possible thereafter.
Read this passage

I. QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT

printed heading

QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT
Read this passage

A. QUALIFICATIONS

printed heading

I am a partner of The NorthBridge Group, Inc (“NorthBridge”).
Read this passage

B. BACKGROUND AND PURPOSE OF AFFIDAVIT

printed heading

This affidavit describes how the Enhanced Reliability Backstop Mechanism (the “Enhanced Backstop”) to PJM Interconnection, LLC’s (“PJM”) Reliability Pricing Model (“RPM”) discussed in Constellation Energy Generation’s (“Constellation”) supporting comments in this proceeding1 and originally proposed…
Read this passage

II. PURPOSE AND OPERATION OF THE ENHANCED BACKSTOP

printed heading

II.
Read this passage

C. CERTAIN DESIGN FEATURES OF THE RPM POTENTIALLY LIMIT

printed heading · Topic match: Reliability and curtailment

For example, a typical new entrant generation resource must weigh the commitment of its full construction capital versus its projected market revenues over a twenty year or more economic life and decide whether the projected revenues are sufficient compensation for the up- front capital…
Read this passage Filed comments: Reliability and curtailment

D. THE ENHANCED BACKSTOP WORKS WITHIN THE STRUCTURE OF THE

printed heading

THE ENHANCED BACKSTOP WORKS WITHIN THE STRUCTURE OF THE RPM TO BRING FORTH ADDITIONAL SUPPLY UNDER TIGHT CONDITIONS 11.
Read this passage

III. THE ENHANCED BACKSTOP WILL INCREASE CONFIDENCE IN PJM MARKETS WHILE

printed heading

THE ENHANCED BACKSTOP WILL INCREASE CONFIDENCE IN PJM MARKETS WHILE MINIMIZING PRICE DISTORTIONS AND OTHER POTENTIAL HARMS
Read this passage

E. THE ENHANCED RELIABILITY BACKSTOP WILL ALLOW PJM MARKETS

printed heading · Topic match: Connecting load and generation

The ability to make multi-year offers at the price cap could provide a pathway for such resources to continue to clear in PJM rather than external markets.  In-development new generation: PJM and neighboring regions have a large volume of new generation working through the interconnection queue…
Read this passage Filed comments: Connecting load and generation

F. THE ENHANCED BACKSTOP HAS BEEN CAREFULLY DESIGNED TO

printed heading

THE ENHANCED BACKSTOP HAS BEEN CAREFULLY DESIGNED TO MINIMIZE ANY HARMS TO PJM COMPETITIVE MARKETS 22.
Read this passage

IV. CERTAIN FEATURES OF THE ENHANCED BACKSTOP COULD BE VARIED TO ACHIEVE A

printed heading · Topic match: Reliability and curtailment

Figure 2 below shows the approximate tradeoff in reliability between different levels of Procurement Threshold, based on my analysis of information provided by PJM during the CIFP- LLA process: 13 Figure 2 Source: Based on PJM Interconnection, LLC, Estimated Preliminary Resource Adequacy Metrics…
Read this passage Filed comments: Reliability and curtailment