Motion for Extension of Time, Shortened Answer Period and Request for Expedited Action of the Indicated PJM Transmission Owners
Text extracted from the eLibrary original (SHA-256 6c7f33058056e06c…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in EL25-49
Topics in the text: Filing procedure · Registry access · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket Nos.Read this passage Filed comments: Filing procedure
I. BACKGROUND
printed heading
BACKGROUND In the December Order, the Commission found “that PJM’s Tariff is unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to generators serving Co- Located Load and Eligible…Read this passage
I. MOTION FOR EXTENSION OF TIME
printed heading · Topic match: Filing procedure
MOTION FOR EXTENSION OF TIME An extension of time for the initial filing deadline10 is warranted because this proceeding involves highly complex and interrelated issues that require careful analysis and coordination between PJM, PJM Transmission Owners, and other PJM stakeholders.Read this passage Filed comments: Filing procedure
II. MOTION FOR SHORTENED ANSWER PERIOD AND EXPEDITED ACTION
printed heading
MOTION FOR SHORTENED ANSWER PERIOD AND EXPEDITED ACTION In light of the circumstances described herein, the PJM Transmission Owners request that the Commission shorten the period for answers to this Motion to three (3) days, making answers due no later than January 20, 2026.Read this passage
III. CONCLUSION
printed heading · Topic match: Connecting load and generation
CONCLUSION As discussed above, the PJM Transmission Owners respectfully request that the Commission grant a 30-day extension of time for the submission of (i) revisions to PJM’s Tariff to effectuate three new forms of transmission service for Co-Located Load; and (ii) initial and reply briefs in…Read this passage Filed comments: Connecting load and generation
CERTIFICATE OF SERVICE
printed heading
Dated in Washington, D.C. this 14th day of January, 2026. /s/ Daniel Klein Daniel Klein Davis Wright Tremaine LLPRead this passage