EL25-49-000 · 2026-01-14 · Indicated PJM Transmission Owners

Motion for Extension of Time, Shortened Answer Period and Request for Expedited Action of the Indicated PJM Transmission Owners

Text extracted from the eLibrary original (SHA-256 6c7f33058056e06c…). Download the original from the official source.

Contents · 4 sections
  1. I. BACKGROUND p. 2
  2. I. MOTION FOR EXTENSION OF TIME p. 3
  3. II. MOTION FOR SHORTENED ANSWER PERIOD AND EXPEDITED ACTION p. 5
  4. III. CONCLUSION p. 6

Read topic-matched comments in EL25-49

Topics in the text: Filing procedure · Registry access · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket Nos.
Read this passage Filed comments: Filing procedure

I. BACKGROUND

printed heading

BACKGROUND In the December Order, the Commission found “that PJM’s Tariff is unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to generators serving Co- Located Load and Eligible…
Read this passage

I. MOTION FOR EXTENSION OF TIME

printed heading · Topic match: Filing procedure

MOTION FOR EXTENSION OF TIME An extension of time for the initial filing deadline10 is warranted because this proceeding involves highly complex and interrelated issues that require careful analysis and coordination between PJM, PJM Transmission Owners, and other PJM stakeholders.
Read this passage Filed comments: Filing procedure

II. MOTION FOR SHORTENED ANSWER PERIOD AND EXPEDITED ACTION

printed heading

MOTION FOR SHORTENED ANSWER PERIOD AND EXPEDITED ACTION In light of the circumstances described herein, the PJM Transmission Owners request that the Commission shorten the period for answers to this Motion to three (3) days, making answers due no later than January 20, 2026.
Read this passage

III. CONCLUSION

printed heading · Topic match: Connecting load and generation

CONCLUSION As discussed above, the PJM Transmission Owners respectfully request that the Commission grant a 30-day extension of time for the submission of (i) revisions to PJM’s Tariff to effectuate three new forms of transmission service for Co-Located Load; and (ii) initial and reply briefs in…
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

Dated in Washington, D.C. this 14th day of January, 2026. /s/ Daniel Klein Daniel Klein Davis Wright Tremaine LLP