PJM Industrial Customer Coalition et al. submit Request for Clarification or, in the Alternative, Rehearing of the 12/18/2025 Order
Text extracted from the eLibrary original (SHA-256 e1ff2cc4aacabdbb…). Download the original from the official source.
Contents · 13 sections
- I. INTRODUCTION
- II. THE CRITICAL ISSUE: EXECUTIVE SUMMARY
- III. STATEMENT OF ISSUES/ERRORS FOR ALTERNATIVE REHEARING
- IV. PROCEDURAL HISTORY
- V. REQUEST FOR CLARIFICATION
- A. Issue #1. The Industrials seek clarification on whether cogeneration QFs under
- B. Issue #2. The Industrials seek clarification that PJM’s new transmission services
- C. Issue #3. The Industrials seek clarification that the removal of “netting” rules for
- D. Issue #4. The Industrials seek clarification that any retail BTMG applicability
- VI. REQUEST FOR REHEARING
- A. STATEMENT OF ISSUES / SPECIFICATION OF ERRORS
- B. ARGUMENT
- VII. CONCLUSION
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Filing procedure · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
EL25-49-000 EL25-49-001 AD24-11-000 EL25-20-000 (Consolidated) REQUEST FOR CLARIFICATION OR, IN THE ALTERNATIVE, REHEARING OF THE INDUSTRIAL CUSTOMER COALITIONS Pursuant to Rule 713 of the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) Rules of Practice and Procedure,1 the PJM…Read this passage Filed comments: Filing procedure
I. INTRODUCTION
printed heading · Topic match: Connecting load and generation
INTRODUCTION The Co-Located Load Order provides PJM Interconnection, L.L.C. (“PJM”) with sweeping guidance to address customer electrical configurations involving both generation and load behind a retail customer’s meter.Read this passage Filed comments: Connecting load and generation
II. THE CRITICAL ISSUE: EXECUTIVE SUMMARY
printed heading · Topic match: Connecting load and generation
An additional concern is that the Order is not clear whether the new transmission services PJM must create for Co-Located Load (“New Services”) must also be offered to load with minimal or no on-site generation.Read this passage Filed comments: Connecting load and generation
III. STATEMENT OF ISSUES/ERRORS FOR ALTERNATIVE REHEARING
printed heading · Topic match: Connecting load and generation
STATEMENT OF ISSUES/ERRORS FOR ALTERNATIVE REHEARING REQUEST If the Commission grants all of the above requested clarifications in full, then the Commission will have absolved the issues and errors raised in the Industrials’ request for rehearing.Read this passage Filed comments: Connecting load and generation
IV. PROCEDURAL HISTORY
printed heading · Topic match: Connecting load and generation
On December 18, 2025, the Commission issued the Co-Located Load Order, requiring PJM to implement changes to its tariff and initiating a paper hearing, among other instructions.Read this passage Filed comments: Connecting load and generation
V. REQUEST FOR CLARIFICATION
printed heading
REQUEST FOR CLARIFICATION The Industrials respectfully request clarification regarding four issues: (1) the ability for cogeneration QFs and other customers with retail BTMG to have access to back-up power service or another reasonable alternative under the “gross load” calculation approach; (2)…Read this passage
A. Issue #1. The Industrials seek clarification on whether cogeneration QFs under
printed heading · Topic match: Reliability and curtailment
To avoid these results, the Commission should clarify that either (1) cogeneration QFs are exempt from the “gross load” approach mandated under the Order; or (2) PJM must include a reasonable “Back-up Power” transmission option that retail BTMG customers, including QFs, can purchase 17 The pending…Read this passage Filed comments: Reliability and curtailment
B. Issue #2. The Industrials seek clarification that PJM’s new transmission services
printed heading · Topic match: Connecting load and generation
The Industrials seek clarification that PJM’s new transmission services must be made available to load-only customers with load flexibility.Read this passage Filed comments: Connecting load and generation
C. Issue #3. The Industrials seek clarification that the removal of “netting” rules for
printed heading · Topic match: Connecting load and generation
The Co-Located Load Order does not provide clear direction on the removal of “netting” rules as they apply to PJM Capacity obligations.Read this passage Filed comments: Connecting load and generation
D. Issue #4. The Industrials seek clarification that any retail BTMG applicability
printed heading · Topic match: Reliability and curtailment
Loss of these facilities, which may occur in some cases if a sufficiently high threshold is not set, would be a significant setback to PJM’s resource adequacy efforts and to grid reliability generally. 23 We understand that industrial combined heat and power (“CHP”) units may, in certain cases,…Read this passage Filed comments: Reliability and curtailment
VI. REQUEST FOR REHEARING
printed heading · Topic match: Filing procedure
REQUEST FOR REHEARING The Industrial Coalitions respectfully request rehearing on the Co-Located Load Order, as set forth below.Read this passage Filed comments: Filing procedure
A. STATEMENT OF ISSUES / SPECIFICATION OF ERRORS
printed heading · Topic match: Connecting load and generation
STATEMENT OF ISSUES / SPECIFICATION OF ERRORS Pursuant to Rule 713(c),26 the Industrials respectfully submit that the Co-Located Load Order’s determinations with respect to PJM’s retail Behind-the-Meter Generation rules are arbitrary and capricious, do not reflect reasoned decision-making, are…Read this passage Filed comments: Connecting load and generation
B. ARGUMENT
printed heading · Topic match: Connecting load and generation
Because both the PJM Tariff and this proceeding treat Co-Located Load (with its associated generation) and retail BTMG (with its associated load) as distinct concepts, a determination affecting retail BTMG must not be treated as a mere corollary of a Co-Located Load ruling.Read this passage Filed comments: Connecting load and generation
VII. CONCLUSION
printed heading · Topic match: Connecting load and generation
CONCLUSION WHEREFORE, the PJM Industrial Customer Coalition and the Industrial Energy Consumers of America respectfully request that the Commission clarify the Co-Located Load Order as set forth herein, or, alternatively, grant rehearing of the Co-Located Load Order for the reasons set forth herein.Read this passage Filed comments: Connecting load and generation
CERTIFICATE OF SERVICE
printed heading
Dated this 20th day of January, 2026. /s/ Matthew L.Read this passage