Answer and Motion for Leave to Answer of the Independent Market Monitor for PJM to the Request for Clarification or, in the Alternative, Rehearing filed on…
Text extracted from the eLibrary original (SHA-256 f5ebf20e117b860a…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Filing procedure · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
This is contrary to the Statement of Principles Regarding PJM provided by the White House and PJM Governors (“Statement of Principles”).5 This is contrary to the Commission’s approach that recognizes the principles of cost causation.6 CEG’s request for clarification is not a clarification but a…Read this passage Filed comments: Filing procedure
I. ANSWER
printed heading
I.Read this passage
A. Generators Should Not Be Permitted to Sell Capacity Twice.
printed heading · Topic match: Connecting load and generation
Contrary to the assumption of CEG, the Commission’s definitions of co-located load and co-located arrangements do not include any statement about whether the co-located load buys capacity from the PJM markets or is somehow not part of PJM markets.7 As defined by the Commission, co-located load does…Read this passage Filed comments: Connecting load and generation
B. No Clarification on Jurisdiction Is Needed.
printed heading · Topic match: Connecting load and generation
CEG requests “clarification” (at 6–7) that the Commission finding that “which generating facilities are sited and allowed to serve Co-Located Load is also a question of state law” does not mean that states can decide which generation facilities are allowed to serve “Co-located Load.” CEG also…Read this passage Filed comments: Connecting load and generation
II. MOTION FOR LEAVE TO ANSWER
printed heading · Topic match: Filing procedure
MOTION FOR LEAVE TO ANSWER The Commission’s Rules of Practice and Procedure, 18 CFR § 385.213(a)(2), do not permit answers to requests for rehearing unless otherwise ordered by the decisional authority.Read this passage Filed comments: Filing procedure
III. CONCLUSION
printed heading · Topic match: Filing procedure
Operator Corp., 129 FERC ¶ 61,241 at P 16 (2009) (“We will accept the answers and responses to the requests for rehearing because they provide information that assisted us in our decision making process.”); ISO New Eng., Inc., 120 FERC ¶ 61,087 at P 30 (2007) (“We will accept the parties’ answers…Read this passage Filed comments: Filing procedure
CERTIFICATE OF SERVICE
printed heading
Dated at Eagleville, Pennsylvania, this 5th day of February, 2026.Read this passage