EL25-49-000 · 2026-02-19 · Pennsylvania Office of Consumer Advocate

Motion for Leave to Answer and Answer of Pennsylvania Office of Consumer Advocate in support of PJM Industrial Customer Coalition's et al. 1/20/2026 Request…

Text extracted from the eLibrary original (SHA-256 5e9f36d8c03feb37…). Download the original from the official source.

Contents · 5 sections
  1. I. Summary of Answer to the ICC’s Request p. 2
  2. II. Background on the Order’s BTMG Provisions p. 3
  3. III. FERC Should Adhere to the Jurisdictional Limits Expressed in the Order to Preserve p. 6
  4. IV. FERC Should Evaluate Whether and How to Set a MW Threshold(s) with Continued p. 8
  5. V. Conclusion p. 12

Read topic-matched comments in EL25-49

Topics in the text: Reliability and curtailment · Cost allocation · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Registry access

EL25-20-000 ) v. ) ) PJM Interconnection, L.L.C. ) (Consolidated) ) MOTION FOR LEAVE TO ANSWER AND ANSWER OF THE PENNSYLVANIA OFFICE OF CONSUMER ADVOCATE The Pennsylvania Office of Consumer Advocate (PA OCA) moves for leave to answer (Motion) and submits this Answer1 in support of the PJM…
Read this passage Filed comments: Registry access

I. Summary of Answer to the ICC’s Request

printed heading · Topic match: Cost allocation

Such a configuration ensures that the load with BTMG does not materially “lean” on PJM.5 In addressing PJM’s BTMG rule, FERC should adhere to the jurisdictional limits expressed in the Order to preserve exclusive state retail authority and protect consumers from cost shifts, because doing so will…
Read this passage Filed comments: Cost allocation

II. Background on the Order’s BTMG Provisions

printed heading · Topic match: Reliability and curtailment

Background on the Order’s BTMG Provisions In the Order, the Commission found PJM’s existing BTMG rules to be no longer just and reasonable because “loads with BTMG are not fully accounted for in resource adequacy planning,” which creates a “potential transmission and resource adequacy planning…
Read this passage Filed comments: Reliability and curtailment

III. FERC Should Adhere to the Jurisdictional Limits Expressed in the Order to Preserve

printed heading · Topic match: Connecting load and generation

The ICC’s Request correctly notes that “the Order does not sufficiently explain the legal basis for asserting jurisdiction over retail customers with [BTMG] that is not otherwise used in PJM’s energy or capacity markets and does not use the PJM transmission system.”24 In accordance with FERC’s…
Read this passage Filed comments: Connecting load and generation

IV. FERC Should Evaluate Whether and How to Set a MW Threshold(s) with Continued

printed heading · Topic match: Reliability and curtailment

Because the proceeding has not yet developed a legally sufficient record on BTMG, FERC and PJM should approach the threshold by continuing to focus where FERC and PJM have been focusing: on “the scale of large data centers” and “very large loads like data centers” that “raise cost shifting…
Read this passage Filed comments: Reliability and curtailment

V. Conclusion

printed heading · Topic match: Registry access

Conclusion The PA OCA respectfully requests that the Commission accept this Answer in support of the ICC’s Request because it should assist the Commission in determining appropriate, end-use- consumer-protective BTMG rules in PJM.
Read this passage Filed comments: Registry access

CERTIFICATE OF SERVICE

printed heading · Topic match: Registry access

Harmar Josiah Harmar Assistant Consumer Advocate Pennsylvania Office of Consumer Advocate PA Attorney ID # 338426 JHarmar@paoca.org