PJM Interconnection, L.L.C. submits Supplemental Informational Report with additional detail regarding the timeline and process for developing the revisions…
Text extracted from the eLibrary original (SHA-256 c7d7b4dd547df203…). Download the original from the official source.
Contents · 2 sections
Read topic-matched comments in EL25-49
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
PJM Interconnection, L.L.C. 2750 Monroe Blvd Audubon, PA 19403 Daniel Vinnik Counsel T: (267) 858-9451 Daniel.Vinnik@pjm.com February 23, 2026 Honorable Debbie-Anne A.Read this passage
I. INFORMATIONAL FILING
printed heading
INFORMATIONAL FILING PJM and stakeholders have commenced the process for developing the reliability backstop procurement construct at the February 6, 2026 Reliability Backstop Procurement Workshop.2 Under the current timeline, PJM is targeting implementation of a reliability backstop procurement 1…Read this passage
II. CONCLUSION
printed heading
CONCLUSION PJM pledges to keep the Commission informed of the timeline for submission of a filing to the Commission if changes to the current timeline become necessary.Read this passage
CERTIFICATE OF SERVICE
printed heading
CERTIFICATE OF SERVICE I hereby certify that I have this 23rd day of February, 2026 caused a copy of the foregoing document to be served upon each person designated on the official service lists compiled by the Secretary in this proceeding. /s/ Daniel Vinnik Daniel Vinnik Counsel PJM…Read this passage