PJM Interconnection, L.L.C. submits second supplemental Information Report re timeline for stakeholder deliberation on the reliability backstop procurement…
Text extracted from the eLibrary original (SHA-256 765668b851bd1d18…). Download the original from the official source.
Contents · 2 sections
Read topic-matched comments in EL25-49
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
PJM Interconnection, L.L.C. 2750 Monroe Blvd Audubon, PA 19403 Daniel Vinnik Counsel T: (267) 858-9451 Daniel.Vinnik@pjm.com March 9, 2026 Honorable Debbie-Anne A.Read this passage
I. INFORMATIONAL FILING
printed heading
INFORMATIONAL FILING Since the February 23, 2026 supplemental informational report, PJM has continued to discuss the framework of a reliability backstop procurement mechanism with stakeholders.Read this passage
II. CONCLUSION
printed heading
CONCLUSION PJM pledges to keep the Commission informed of the timeline for submission of a filing to the Commission if changes to the current timeline become necessary.Read this passage
CERTIFICATE OF SERVICE
printed heading
CERTIFICATE OF SERVICE I hereby certify that I have this 9th day of March, 2026 caused a copy of the foregoing document to be served upon each person designated on the official service lists compiled by the Secretary in this proceeding. /s/ Daniel Vinnik Daniel Vinnik Counsel PJM Interconnection,…Read this passage