EL25-49-000 · 2026-03-09 · PJM Interconnection, L.L.C.

Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C. to the 02/20/2026 Motion for Leave to Answer and Answer, and the 01/20/2026 Request for…

Text extracted from the eLibrary original (SHA-256 33ffc26cb9e23e64…). Download the original from the official source.

Contents · 4 sections
  1. I. ANSWER p. 4
  2. A. Capacity Resources Cannot and Should Not Be Permitted to Receive p. 4
  3. II. MOTION FOR LEAVE TO ANSWER p. 7
  4. III. CONCLUSION p. 7

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Filing procedure · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

Indeed, even the Requester admits that the existing energy market must offer requirements and energy offer price rules, which are outside the scope of this proceeding, would need to be modified in order to allow a resource to principally serve the Co-Located Load, except only during emergencies,…
Read this passage Filed comments: Connecting load and generation

I. ANSWER

printed heading

I.
Read this passage

A. Capacity Resources Cannot and Should Not Be Permitted to Receive

printed heading · Topic match: Connecting load and generation

This statement is a caveat to the Commission’s directive that PJM require “non-emergency generation capacity resources to submit offers for” reserves by clarifying that resources that have met their must-offer requirement but haven’t been committed in the Day-ahead Energy Market as reserves should…
Read this passage Filed comments: Connecting load and generation

II. MOTION FOR LEAVE TO ANSWER

printed heading · Topic match: Filing procedure

MOTION FOR LEAVE TO ANSWER Although the Commission’s rules do not generally permit answers to requests for rehearing,26 the Commission will accept such an answer where, as here, it assists the Commission in its decision-making process.27 PJM therefore respectfully requests that the Commission grant…
Read this passage Filed comments: Filing procedure

III. CONCLUSION

printed heading

Audubon, PA* 19403 (*Licensed in the District of Columbia and Illinois) (267) 858-9451 (phone) daniel.vinnik@pjm.com March 9, 2026 Counsel for PJM Interconnection, L.L.C.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Audubon, PA 19403 (267) 858-9451 (phone) daniel.vinnik@pjm.com Attorney for PJM Interconnection, L.L.C.