Comments of Digital Power Network on the 02/23/2026 compliance filing submitted by PJM Interconnection, L.L.C
Text extracted from the eLibrary original (SHA-256 92727e823e0bfeed…). Download the original from the official source.
Contents · 7 sections
- I. BACKGROUND
- II. COMMENTS
- A. The Commission should ensure that PJM’s new co-located load transmission service
- B. The Commission should ensure that the final framework continues to support demand
- C. The Commission should require further consideration of PJM’s proposed 50 MW cap on
- D. The Commission should not require projects to rely on a framework that may compound
- III. CONCLUSION
Read topic-matched comments in ER26-1479
Topics in the text: Connecting load and generation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
EL25-49, et al., which directed PJM to revise its behind-the-meter generation tariff provisions, establish new transmission service pathways for co-located load, and revise its necessary studies process.2 DPN appreciates the Commission’s and PJM’s efforts to bring greater clarity to the treatment…Read this passage Filed comments: Connecting load and generation
I. BACKGROUND
printed heading · Topic match: Connecting load and generation
EL25-49, et al.3 PJM states that the filing addresses three principal matters: revisions to retail behind-the-meter generation (“Retail BTMG”), the establishment of new transmission services for eligible customers taking service on behalf of co-located load, and revisions to the necessary studies…Read this passage Filed comments: Connecting load and generation
II. COMMENTS
printed heading
COMMENTS 3 Feb. 23 Compliance Filing at 1-3. 4 Id. at 1-3. 5 Id. at 2-3. 6 Id. at 7-9. 7 Id. at 7. 8 Id. at 1-3; December 18 Order at 2-4, 96-103. 9 December 18 Order at 96-97. 10 Feb. 23 Compliance Filing at 26Read this passage
A. The Commission should ensure that PJM’s new co-located load transmission service
printed heading · Topic match: Connecting load and generation
The Commission should ensure that PJM’s new co-located load transmission service framework preserves the operational flexibility of flexible loads.Read this passage Filed comments: Connecting load and generation
B. The Commission should ensure that the final framework continues to support demand
printed heading · Topic match: Reliability and curtailment
Accordingly, the Commission should clarify that PJM’s compliance revisions must be implemented in a manner that preserves appropriate opportunities for flexible loads to participate in demand response and other reliability-supporting arrangements as both a business and reliability activity,…Read this passage Filed comments: Reliability and curtailment
C. The Commission should require further consideration of PJM’s proposed 50 MW cap on
printed heading
The Commission should require further consideration of PJM’s proposed 50 MW cap on new Retail BTMG.Read this passage
D. The Commission should not require projects to rely on a framework that may compound
printed heading · Topic match: Connecting load and generation
DPN is particularly concerned that PJM’s proposed treatment of large BTMG resources above 50 MW may force more projects into interconnection and study pathways at a time when PJM’s interconnection queue and associated study timelines remain a major barrier to infrastructure deployment.Read this passage Filed comments: Connecting load and generation
III. CONCLUSION
printed heading · Topic match: Connecting load and generation
DPN respectfully requests that the Commission accept PJM’s compliance filing only to the extent it provides needed tariff clarity, while requiring further clarification and modification to ensure that the final framework preserves the operational flexibility of large flexible loads, maintains…Read this passage Filed comments: Connecting load and generation