Limited Protest of Advanced Energy United et al. in response to PJM Interconnection, L.L.C.’s 02/23/2026 compliance filing
Text extracted from the eLibrary original (SHA-256 916f72f53f857158…). Download the original from the official source.
Contents · 6 sections
Read topic-matched comments in ER26-1479
Topics in the text: Connecting load and generation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
The comments expressed in this filing represent the position of Advanced Energy United but may not represent the views of any particular member. 3 The comments contained in this filing represent the position of SEIA as a trade organization on behalf of the solar industry, but do not necessarily…Read this passage Filed comments: Connecting load and generation
I. Background
printed heading · Topic match: Reliability and curtailment
This has placed significant stress on the region’s ability to meet its resource adequacy requirements, at a time when the interconnection of new generation has been stalled as PJM works through a backlog of requests and implements new reforms.Read this passage Filed comments: Reliability and curtailment
II. Limited Protest
printed heading
II.Read this passage
A. BTMG rules are overly restrictive and do not accommodate optimized
printed heading
Any revised proposal from PJM must set a materiality threshold 5 based on the customer’s netting, not the nameplate capacity of the BTMG.Read this passage
B. Transition and Grandfathering Rules Must Ensure a Smooth Transition to
printed heading · Topic match: Reliability and curtailment
The temporary closure of PJM’s interconnection queue to new generation,12 significant 12 PJM effectively closed its interconnection process to new applicants in 2022 and expects to initiate the first cluster study of new requests in April 2026.Read this passage Filed comments: Reliability and curtailment
C. Streamlining Interconnection for Non-Exporting Co-Located Facilities
printed heading · Topic match: Connecting load and generation
These projects do not require deliverability given their intent to serve only the co-located load; given that they will rarely, if ever, trigger network upgrades, subjecting them to the standard queue process is a purely administrative hurdle with no technical or reliability benefit, but…Read this passage Filed comments: Connecting load and generation
III. Conclusion
printed heading · Topic match: Reliability and curtailment
Yet overly rigid rules that hinder innovative behind the meter configurations; transition and grandfathering rules that limit, rather than expand, opportunities for behind the meter and co-located resources to contribute to meeting resource adequacy needs in PJM; and unnecessarily cumbersome…Read this passage Filed comments: Reliability and curtailment
CERTIFICATE OF SERVICE
printed heading
Dated this 16th day of March 2026. /s/ Mike HaughRead this passage