Joint Protest of the PJM Industrial Customer Coalition et al. in response to PJM Interconnection, L.L.C.’s 60-Day Compliance Filing for Co-Located Load…
Text extracted from the eLibrary original (SHA-256 550029d9f6ed934d…). Download the original from the official source.
Contents · 25 sections
- I. BACKGROUND
- II. THE INDUSTRIALS/AMTRAK
- III. EXECUTIVE SUMMARY
- IV. PROTEST
- A. PJM’s proposed exemption for PURPA Qualifying Facilities is appropriate,
- B. PJM’s Proposed 50 MW Retail Threshold is insufficient to balance the
- C. The FERC should direct PJM to remove the “all-or-nothing” approach to the
- V. COMMENTS
- A. Grandfathering rules and confirmation of grandfathered status should be
- B. PJM’s exemption for back-up generation is appropriate and should be
- VI. CONCLUSION & REQUEST FOR RELIEF
- II. BACKGROUND ON THE USE OF COGENERATION FACILITIES BY
- III. COMMERCIAL, INDUSTRIAL AND INSTITUTIONAL CUSTOMERS
- IV. FOR TRADITIONAL LARGE LOADS SERVED BY COGENERATION
- V. FIRM CONTRACT DEMAND TRANSMISSION SERVICE AND
- VI. PJM’S PROPOSAL WITH RESPECT TO ALLOWING EXISTING
- VII. PJM’S PROPOSED 50 MW AND SMALLER LIMITATION FOR
- I. INTRODUCTION
- II. BACKGROUND ON THE USE OF COGENERATION FACILITIES BY
- III. COMMERCIAL, INDUSTRIAL AND INSTITUTIONAL CUSTOMERS USING
- IV. FOR TRADITIONAL LARGE LOADS SERVED BY COGENERATION
- V. FIRM CONTRACT DEMAND TRANSMISSION SERVICE AND NON-FIRM
- VI. PJM’S PROPOSAL WITH RESPECT TO ALLOWING EXISTING CERTIFIED
- VII. PJM’S PROPOSED 50 MW AND SMALLER LIMITATION FOR NON-
- VIII. CONCLUSION
Read topic-matched comments in ER26-1479
Topics in the text: Reliability and curtailment · Cost allocation · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) ) ) ) Docket No.Read this passage Filed comments: Connecting load and generation
I. BACKGROUND
printed heading · Topic match: Cost allocation
BACKGROUND On December 18, 2025, the Commission issued the Order, finding that the PJM Tariff is unjust and unreasonable due to the lack of specificity for the rates, terms, and conditions that apply to Co-Located Load and directing PJM to make several compliance and informational filings.Read this passage Filed comments: Cost allocation
II. THE INDUSTRIALS/AMTRAK
printed heading · Topic match: Filing procedure
Unlike the surge in large-load demands from data centers and computational workloads, most manufacturers are simply trying to survive and keep their facilities 8 PJMICC and IECA (together, “Requestors”) jointly filed a Request For Clarification or, in the Alternative, Rehearing of the Industrial…Read this passage Filed comments: Filing procedure
III. EXECUTIVE SUMMARY
printed heading · Topic match: Reliability and curtailment
U-21859). 13 See Order at PP 221 (directing PJM “to propose a new MW threshold for the amount of load at a particular electrical location that Network Customers may net by using BTMG”). 14 Order at P 4 (“As explained in the Show Cause Order, Co-Location Arrangements are becoming increasingly common…Read this passage Filed comments: Reliability and curtailment
IV. PROTEST
printed heading · Topic match: Reliability and curtailment
For some industrial and institutional customers, transmission and capacity cost savings are a critical factor that makes it worth the investment to build and operate generation on their premises—investments these customers have already made (sometimes over decades).39 Absent a reasonable…Read this passage Filed comments: Reliability and curtailment
A. PJM’s proposed exemption for PURPA Qualifying Facilities is appropriate,
printed heading · Topic match: Cost allocation
However, the law permits the Commission to deem certain QFs as having sufficient market access that the applicable utility is excused from its must-purchase obligation.66 After many utilities terminated their mandatory purchase obligations in the wake of the development of organized wholesale…Read this passage Filed comments: Cost allocation
B. PJM’s Proposed 50 MW Retail Threshold is insufficient to balance the
printed heading · Topic match: Reliability and curtailment
However, the 72 See Dauphinais Affidavit at 67 (referencing data and regulatory developments in Michigan demonstrating that a 300 MW threshold is supportable considering data center MW load requests). 26 Industrials/Amtrak respectfully suggest that one of the primary considerations should be the…Read this passage Filed comments: Reliability and curtailment
C. The FERC should direct PJM to remove the “all-or-nothing” approach to the
printed heading · Topic match: Connecting load and generation
On a related note, the fact that a retail customer engages in sales of excess energy must not disqualify the customer from netting its retail BTMG.Read this passage Filed comments: Connecting load and generation
V. COMMENTS
printed heading
COMMENTS The Industrials/Amtrak believe that PJM’s proposals on back-up generation and grandfathering are reasonable interpretations and implementation of the Order.Read this passage
A. Grandfathering rules and confirmation of grandfathered status should be
printed heading
All existing BTMG-related contracts, including those that renew year by year, must be honored to avoid serious, unwarranted harm to these retail customers, such as Amtrak.Read this passage
B. PJM’s exemption for back-up generation is appropriate and should be
printed heading · Topic match: Reliability and curtailment
It also potentially provides additional resource adequacy strength to be prepared for emergencies.Read this passage Filed comments: Reliability and curtailment
VI. CONCLUSION & REQUEST FOR RELIEF
printed heading
CONCLUSION & REQUEST FOR RELIEF The Industrials/Amtrak respectfully request that the Commission reject PJM’s Compliance Filing, consistent with this Protest, and direct PJM to file a new compliance filing, consistent with the above Protest and Comments.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated this 16th day of March, 2026. /s/ Matthew L.Read this passage
Table of Contents
printed heading
Table of Contents I.Read this passage
II. BACKGROUND ON THE USE OF COGENERATION FACILITIES BY
printed heading
II.Read this passage
III. COMMERCIAL, INDUSTRIAL AND INSTITUTIONAL CUSTOMERS
printed heading
III.Read this passage
IV. FOR TRADITIONAL LARGE LOADS SERVED BY COGENERATION
printed heading
IV.Read this passage
V. FIRM CONTRACT DEMAND TRANSMISSION SERVICE AND
printed heading
V.Read this passage
VI. PJM’S PROPOSAL WITH RESPECT TO ALLOWING EXISTING
printed heading
VI.Read this passage
VII. PJM’S PROPOSED 50 MW AND SMALLER LIMITATION FOR
printed heading · Topic match: Reliability and curtailment
PJMICC PRA PJM Industrial Customer Coalition Planning Resource Auction PURPA Public Utility Regulatory Policies Act of 1978 RAA Reliability Assurance Agreement RAR Resource Adequacy Requirements SMR Small Modular Reactors Exhibit No.Read this passage Filed comments: Reliability and curtailment
I. INTRODUCTION
printed heading · Topic match: Cost allocation
For at least twenty-six (26) years, I have also participated in the Midcontinent Independent System Operator, Inc. (“MISO”) stakeholder process on behalf of several large end-use customer groups.1 This has included, but not been limited to, providing extensive feedback to MISO and other MISO…Read this passage Filed comments: Cost allocation
II. BACKGROUND ON THE USE OF COGENERATION FACILITIES BY
printed heading · Topic match: Cost allocation
This is because the thermal energy needs of the retail customer typically dictate how much electric power must be produced by the Cogeneration Facility.Read this passage Filed comments: Cost allocation
III. COMMERCIAL, INDUSTRIAL AND INSTITUTIONAL CUSTOMERS USING
printed heading · Topic match: Cost allocation
Due to these differences, from a cost causation perspective, very large computational load co-located behind the meter of generation facilities are more akin to wholesale customer load served by utility behind the meter generation21 than traditional large commercial, industrial, and institutional…Read this passage Filed comments: Cost allocation
IV. FOR TRADITIONAL LARGE LOADS SERVED BY COGENERATION
printed heading · Topic match: Cost allocation
FOR TRADITIONAL LARGE LOADS SERVED BY COGENERATION FACILITIES, PJM’S CURRENT RETAIL BEHIND THE METER GENERATION PROVISIONS ARE CONSISTENT WITH COST CAUSATION AND FERC’S OWN BACKUP AND MAINTENANCE POWER RULES FOR QUALIFYING FACILITIES 27.Read this passage Filed comments: Cost allocation
V. FIRM CONTRACT DEMAND TRANSMISSION SERVICE AND NON-FIRM
printed heading · Topic match: Connecting load and generation
EL25-49-000, PJM in its February 23, 2026 initial brief in that paper hearing (“PJM Paper Hearing Initial Brief”) in part proposed: The entire gross load of the Co-Located Load be covered by a combination of Firm Contract Demand Transmission Service and Non- Firm Contract Demand Transmission…Read this passage Filed comments: Connecting load and generation
VI. PJM’S PROPOSAL WITH RESPECT TO ALLOWING EXISTING CERTIFIED
printed heading · Topic match: Connecting load and generation
It is important to note that providing legacy retail behind-the-meter generation netting treatment for all Qualifying Facilities would not provide a “back door” for very large computational loads to bypass the Co-Located Load provisions of FERC’s December 18, 2025, Show Cause Order in Docket No.Read this passage Filed comments: Connecting load and generation
VII. PJM’S PROPOSED 50 MW AND SMALLER LIMITATION FOR NON-
printed heading
EL25-49-000, et al.48 PJM also notes that, given these retail behind the meter generation arrangements, like those for PURPA Qualifying Facilities, have been in place and netted against Network Loads within PJM without known operational issues to date, it proposes to allow such arrangements, which…Read this passage
VIII. CONCLUSION
printed heading · Topic match: Cost allocation
IA-1 Attachment 3 Page 3 of 3 ICC Docket Nos. 25-0677 & 25-0679 (Cons.) Commonwealth Edison Company’s Response to NRG Energy, Inc. (“NRG”) Information Requests NRG-ComEd 1.01-NRG-ComEd 1.20 Date Received: August 22, 2025 Date Served: August 29, 2025 REQUEST NO.Read this passage Filed comments: Cost allocation