Comments of Data Center Coalition in response to PJM Interconnection, L.L.C.’s 02/23/2026 tariff filing in compliance
Text extracted from the eLibrary original (SHA-256 9f6ac6cfd38aecf1…). Download the original from the official source.
Contents · 2 sections
Read topic-matched comments in ER26-1479
Topics in the text: Reliability and curtailment · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No.Read this passage
Introduction
printed heading · Topic match: Reliability and curtailment
Further, PJM must define the trigger, scope, and sequence of Interim NITS curtailment with respect to the operational limitations identified in the study and should not be able to curtail 6PJM Staff Preliminary/Working Draft of Concepts as of January 23, 2026. 6 load for unrelated broader resource…Read this passage Filed comments: Reliability and curtailment
Conclusion
printed heading
Conclusion DCC appreciates FERC’s leadership and innovation in pushing forward new transmission services in PJM.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, DC this 16th day of March 2026. /s/ Lucas Fykes Lucas Fykes Senior Director, Energy Policy & Regulatory Counsel 1250 H Street, NW, Suite 880 Washington, DC, 20005 lucas@datacentercoalition.org 10Read this passage