Joint Protest of Calibrant Energy et al. to PJM Interconnection, LLC’s proposed revisions to its Open Access Transmission Tariff
Text extracted from the eLibrary original (SHA-256 621e9d0f5576fd69…). Download the original from the official source.
Contents · 6 sections
Read topic-matched comments in ER26-1479
Topics in the text: Reliability and curtailment · Cost allocation · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
PJM’s proposed Retail BTMG definition must be rejected because it does not comply with the Commission’s directives in the Co-Location Order.Read this passage Filed comments: Reliability and curtailment
I. BTMG PARTIES’ INTEREST IN THE PROCEEDING
printed heading · Topic match: Reliability and curtailment
Granting this limited protest will critically support development of BTMG resources while managing reliability and resource adequacy risks.6Read this passage Filed comments: Reliability and curtailment
II. ARGUMENT
printed heading
II.Read this passage
A. The Commission must reject PJM’s BTMG materiality threshold because it
printed heading · Topic match: Reliability and curtailment
The Commission must reject PJM’s BTMG materiality threshold because it does not comply with the Co-Location Order, is not just and reasonable, and is unduly discriminatory. 6 Co-Location Order, 193 FERC ¶ 61,217 at PP 186, 221. 5 1.Read this passage Filed comments: Reliability and curtailment
B. If the Commission accepts PJM’s non-compliant nameplate capacity-based
printed heading · Topic match: Reliability and curtailment
PJM asks, if the Commission does not accept PJM’s proposed Retail BTMG revisions, for the Commission to “allow an interim materiality threshold to be in place for the start of the transition period,” potentially to be further refined in later filings.22 As to the potential level of this interim…Read this passage Filed comments: Reliability and curtailment
C. The Commission must reject PJM’s BTMG grandfathering provisions
printed heading · Topic match: Connecting load and generation
The Commission must reject PJM’s BTMG grandfathering provisions because the proposed transition period and grandfathering deadlines are unjust and unreasonable to existing BTMG customers.Read this passage Filed comments: Connecting load and generation
III. CONCLUSION
printed heading
CONCLUSION BTMG Parties respectfully request that the Commission reject PJM’s compliance filing and direct PJM to file revisions that (1) impose a materiality threshold for qualifying as BTMG based on the amount of load a customer may net, or, in the alternative, increase the nameplate threshold to…Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated: March 16, 2026 /s/ Nathan Lobel Nathan Lobel Roselle LLP 300 New Jersey Ave.Read this passage