Protest and Comments of Constellation Energy Generation, LLC in response to PJM Interconnection, L.L.C.’s 02/23/2026 60-Day Compliance Filing
Text extracted from the eLibrary original (SHA-256 103941dad9c04bde…). Download the original from the official source.
Contents · 10 sections
- I. The Commission Should Reject PJM’s New Definition of Co-Located Load as Outside
- II. The Commission Should Reject PJM’s 50-MW Materiality Threshold for BTMG, or in
- I. The Commission Should Require PJM to Clarify the Necessary Studies Process for
- A. Additional Clarification on the Scope of the Necessary Studies Process Is
- B. New Requirements Regarding Necessary Studies Should Not Retroactively
- C. Speed to Market Demands Deadlines for Completing the Necessary Studies
- II. The Proposed Definition of Co-Located Generating Facility Should Be Limited to the
- III. The Commission Should Require Other Modifications to Ensure Interim NITS
- IV. The Commission Should Clarify that Capacity Serving Non-Firm Load Need Not Delist
- CONCLUSION
Read topic-matched comments in ER26-1479
Topics in the text: Connecting load and generation · Filing procedure · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
ER26-1479- 000 (Feb. 23, 2026) (“Sixty-Day Compliance Filing”). 3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18th Order”). 4 NorthWestern Corp., 113 FERC ¶ 61,215, at P 9 (2005) (“The Commission has long established that compliance filings must be limited to the specific…Read this passage Filed comments: Connecting load and generation
I. The Commission Should Reject PJM’s New Definition of Co-Located Load as Outside
printed heading · Topic match: Connecting load and generation
Accordingly, the Commission should reject PJM’s new definition of Co-Located Load.”). 6 See Sixty-Day Compliance Filing at 31-35; id. at Exhibit B (“Marked Tariff”) at 12, 74-75, 81-82. 7 December 18th Order, 193 FERC ¶ 61,217 at P 164. 8 Non-RTO/ISO transmission providers seeking deviations from…Read this passage Filed comments: Connecting load and generation
II. The Commission Should Reject PJM’s 50-MW Materiality Threshold for BTMG, or in
printed heading · Topic match: Connecting load and generation
To the extent that the gross demand of a Co-Located Load is not covered by the Eligible Customer’s Firm Contract Demand Transmission Service, the Eligible Customer must cover the remaining gross demand by applying for Non-Firm Contract Demand Transmission Service.Read this passage Filed comments: Connecting load and generation
I. The Commission Should Require PJM to Clarify the Necessary Studies Process for
printed heading · Topic match: Connecting load and generation
The Commission Should Require PJM to Clarify the Necessary Studies Process for Project Developers to Ensure Speed to Market To achieve speed to market, we recommend three clarifications to PJM’s proposed Necessary Studies Tariff language: (1) clarify the scope of the Necessary Studies analysis to…Read this passage Filed comments: Connecting load and generation
A. Additional Clarification on the Scope of the Necessary Studies Process Is
printed heading · Topic match: Connecting load and generation
Project Developer shall be responsible for the costs of any modifications or Network Upgrades identified by Transmission Provider to maintain transmission system reliability, as applicable, as a result of the change to the Interconnection Service Agreement or Generation Interconnection Agreement to…Read this passage Filed comments: Connecting load and generation
B. New Requirements Regarding Necessary Studies Should Not Retroactively
printed heading · Topic match: Connecting load and generation
PJM Interconnection, L.L.C., 162 FERC ¶ 61,296 (2018). 52 Marked Tariff, Part VII, Subpart A, section 401.H.3.b.(i)(b). 15 submitted requests for Necessary Studies prior to implementation of these new requirements will be allowed to rely on the results of those studies to the extent relevant in…Read this passage Filed comments: Connecting load and generation
C. Speed to Market Demands Deadlines for Completing the Necessary Studies
printed heading · Topic match: Connecting load and generation
Specifically, PJM’s proposed requirement that “[t]he Eligible Customer has been designated to take transmission service on behalf of a Co-Located Load in the Application and Study Agreement or the Generation Interconnection Agreement”56 does nothing to reduce concerns about, or affect, how…Read this passage Filed comments: Connecting load and generation
II. The Proposed Definition of Co-Located Generating Facility Should Be Limited to the
printed heading · Topic match: Connecting load and generation
PJM proposes to define “Co-Located Generating Facility” as “an existing or planned Generating Facility that is physically connected to a Co-Located Load.”59 PJM’s proposed definition could be interpreted as applying to the entire Generating Facility based solely on physical connection to a…Read this passage Filed comments: Connecting load and generation
III. The Commission Should Require Other Modifications to Ensure Interim NITS
printed heading · Topic match: Connecting load and generation
First, in Part III of the Tariff, a load’s “option to seek” Interim NITS should be replaced with an “option to take.” This modification conforms the Tariff with the December 18th Order, which stated that Interim Network Integration Transmission Service “must allow an Eligible Customer that has…Read this passage Filed comments: Connecting load and generation
IV. The Commission Should Clarify that Capacity Serving Non-Firm Load Need Not Delist
printed heading · Topic match: Connecting load and generation
The Commission Should Clarify that Capacity Serving Non-Firm Load Need Not Delist and Direct Further Compliance PJM’s proposed Tariff revisions direct that the “Project Developer shall provide Transmission Provider with all information needed to perform the Necessary Studies” including “the amount…Read this passage Filed comments: Connecting load and generation
CONCLUSION
printed heading
CONCLUSION For the reasons stated above, Constellation respectfully requests that the Commission grant this protest and accept these comments and direct further compliance to ensure PJM’s Tariff follows the directives of the December 18th Order.Read this passage
CERTIFICATE OF SERVICE
printed heading
CERTIFICATE OF SERVICE I hereby certify that I have on this 16th day of March, 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R.…Read this passage