ER26-1479-000 · 2026-03-16 · Constellation Energy Generation, LLC

Protest and Comments of Constellation Energy Generation, LLC in response to PJM Interconnection, L.L.C.’s 02/23/2026 60-Day Compliance Filing

Text extracted from the eLibrary original (SHA-256 103941dad9c04bde…). Download the original from the official source.

Contents · 10 sections
  1. I. The Commission Should Reject PJM’s New Definition of Co-Located Load as Outside p. 2
  2. II. The Commission Should Reject PJM’s 50-MW Materiality Threshold for BTMG, or in p. 8
  3. I. The Commission Should Require PJM to Clarify the Necessary Studies Process for p. 12
  4. A. Additional Clarification on the Scope of the Necessary Studies Process Is p. 12
  5. B. New Requirements Regarding Necessary Studies Should Not Retroactively p. 14
  6. C. Speed to Market Demands Deadlines for Completing the Necessary Studies p. 16
  7. II. The Proposed Definition of Co-Located Generating Facility Should Be Limited to the p. 17
  8. III. The Commission Should Require Other Modifications to Ensure Interim NITS p. 18
  9. IV. The Commission Should Clarify that Capacity Serving Non-Firm Load Need Not Delist p. 19
  10. CONCLUSION p. 21

Read topic-matched comments in ER26-1479

Topics in the text: Connecting load and generation · Filing procedure · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

ER26-1479- 000 (Feb. 23, 2026) (“Sixty-Day Compliance Filing”). 3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18th Order”). 4 NorthWestern Corp., 113 FERC ¶ 61,215, at P 9 (2005) (“The Commission has long established that compliance filings must be limited to the specific…
Read this passage Filed comments: Connecting load and generation

I. The Commission Should Reject PJM’s New Definition of Co-Located Load as Outside

printed heading · Topic match: Connecting load and generation

Accordingly, the Commission should reject PJM’s new definition of Co-Located Load.”). 6 See Sixty-Day Compliance Filing at 31-35; id. at Exhibit B (“Marked Tariff”) at 12, 74-75, 81-82. 7 December 18th Order, 193 FERC ¶ 61,217 at P 164. 8 Non-RTO/ISO transmission providers seeking deviations from…
Read this passage Filed comments: Connecting load and generation

II. The Commission Should Reject PJM’s 50-MW Materiality Threshold for BTMG, or in

printed heading · Topic match: Connecting load and generation

To the extent that the gross demand of a Co-Located Load is not covered by the Eligible Customer’s Firm Contract Demand Transmission Service, the Eligible Customer must cover the remaining gross demand by applying for Non-Firm Contract Demand Transmission Service.
Read this passage Filed comments: Connecting load and generation

I. The Commission Should Require PJM to Clarify the Necessary Studies Process for

printed heading · Topic match: Connecting load and generation

The Commission Should Require PJM to Clarify the Necessary Studies Process for Project Developers to Ensure Speed to Market To achieve speed to market, we recommend three clarifications to PJM’s proposed Necessary Studies Tariff language: (1) clarify the scope of the Necessary Studies analysis to…
Read this passage Filed comments: Connecting load and generation

A. Additional Clarification on the Scope of the Necessary Studies Process Is

printed heading · Topic match: Connecting load and generation

Project Developer shall be responsible for the costs of any modifications or Network Upgrades identified by Transmission Provider to maintain transmission system reliability, as applicable, as a result of the change to the Interconnection Service Agreement or Generation Interconnection Agreement to…
Read this passage Filed comments: Connecting load and generation

B. New Requirements Regarding Necessary Studies Should Not Retroactively

printed heading · Topic match: Connecting load and generation

PJM Interconnection, L.L.C., 162 FERC ¶ 61,296 (2018). 52 Marked Tariff, Part VII, Subpart A, section 401.H.3.b.(i)(b). 15 submitted requests for Necessary Studies prior to implementation of these new requirements will be allowed to rely on the results of those studies to the extent relevant in…
Read this passage Filed comments: Connecting load and generation

C. Speed to Market Demands Deadlines for Completing the Necessary Studies

printed heading · Topic match: Connecting load and generation

Specifically, PJM’s proposed requirement that “[t]he Eligible Customer has been designated to take transmission service on behalf of a Co-Located Load in the Application and Study Agreement or the Generation Interconnection Agreement”56 does nothing to reduce concerns about, or affect, how…
Read this passage Filed comments: Connecting load and generation

II. The Proposed Definition of Co-Located Generating Facility Should Be Limited to the

printed heading · Topic match: Connecting load and generation

PJM proposes to define “Co-Located Generating Facility” as “an existing or planned Generating Facility that is physically connected to a Co-Located Load.”59 PJM’s proposed definition could be interpreted as applying to the entire Generating Facility based solely on physical connection to a…
Read this passage Filed comments: Connecting load and generation

III. The Commission Should Require Other Modifications to Ensure Interim NITS

printed heading · Topic match: Connecting load and generation

First, in Part III of the Tariff, a load’s “option to seek” Interim NITS should be replaced with an “option to take.” This modification conforms the Tariff with the December 18th Order, which stated that Interim Network Integration Transmission Service “must allow an Eligible Customer that has…
Read this passage Filed comments: Connecting load and generation

IV. The Commission Should Clarify that Capacity Serving Non-Firm Load Need Not Delist

printed heading · Topic match: Connecting load and generation

The Commission Should Clarify that Capacity Serving Non-Firm Load Need Not Delist and Direct Further Compliance PJM’s proposed Tariff revisions direct that the “Project Developer shall provide Transmission Provider with all information needed to perform the Necessary Studies” including “the amount…
Read this passage Filed comments: Connecting load and generation

CONCLUSION

printed heading

CONCLUSION For the reasons stated above, Constellation respectfully requests that the Commission grant this protest and accept these comments and direct further compliance to ensure PJM’s Tariff follows the directives of the December 18th Order.