EL25-49-000 · 2026-03-24 · Constellation Energy Generation, LLC

Motion for Leave to Answer and Second Answer of Constellation Energy Generation, LLC in response to the Answer filed by PJM Interconnection, L.L.C

Text extracted from the eLibrary original (SHA-256 33c2bb34b328ed03…). Download the original from the official source.

Contents · 4 sections
  1. I. Allowing Capacity Resources Serving Non-Firm, Recallable Co-Located Loads to p. 1
  2. II. PJM’s Arguments Distinguishing Non-Firm Exports from Co-Located Loads are p. 3
  3. III. The Commission Has Broad Authority to Require Changes p. 4
  4. CONCLUSION p. 7

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al.
Read this passage

I. Allowing Capacity Resources Serving Non-Firm, Recallable Co-Located Loads to

printed heading · Topic match: Connecting load and generation

Fourth, it respects the purpose served by the energy market must-offer obligation, consistent with the definition of the Capacity Product.
Read this passage Filed comments: Connecting load and generation

II. PJM’s Arguments Distinguishing Non-Firm Exports from Co-Located Loads are

printed heading · Topic match: Connecting load and generation

PJM’s Arguments Distinguishing Non-Firm Exports from Co-Located Loads are Irrelevant PJM’s attempt to distinguish exports from Co-Located Load arrangements misses the point.
Read this passage Filed comments: Connecting load and generation

III. The Commission Has Broad Authority to Require Changes

printed heading · Topic match: Connecting load and generation

The Commission and PJM could also consider exempting capacity resources serving non- firm Co-Located Load from the energy market must-offer rule.
Read this passage Filed comments: Connecting load and generation

CONCLUSION

printed heading · Topic match: Reliability and curtailment

CONCLUSION For the reasons stated above, Constellation respectfully requests that the Commission accept this Answer and grant its Clarification Request.
Read this passage Filed comments: Reliability and curtailment

CERTIFICATE OF SERVICE

printed heading

CERTIFICATE OF SERVICE I hereby certify that I have on this 24th day of March 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §…
Read this passage