EL25-49-000 · 2026-03-25 · Data Center Coalition

Response of Data Center Coalition to the 02/23/2026 Initial Brief of PJM Interconnection, L.L.C. and the 02/23/2026 Initial Brief of the PJM Transmission…

Text extracted from the eLibrary original (SHA-256 1c32cbd4542be208…). Download the original from the official source.

Contents · 8 sections
  1. I. Introduction p. 1
  2. II. PJM’s Clarifications Confirm that the Proposed Framework Does Not Preserve the p. 2
  3. III. The Proposal Unnecessarily Restricts the Use of Non-Firm Service and Precludes p. 4
  4. IV. The Proposal Does Not Provide a Workable Pathway for Phased Development or p. 6
  5. V. Curtailment Risk and Operational Parameters Remain Insufficiently Defined p. 7
  6. VI. The Proposal is Materially Incomplete and Relies on Future Developments p. 8
  7. VII. The Proposed Implementation Timeline Warrants Refinement p. 9
  8. VIII. Conclusion p. 9

Read topic-matched comments in EL25-49

Topics in the text: Reliability and curtailment · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al ) Docket Nos.
Read this passage

I. Introduction

printed heading · Topic match: Connecting load and generation

Instead, the proposals introduce significant operational rigidity, limit flexibility, and create disincentives that will impede the development of co-located load and associated generation.
Read this passage Filed comments: Connecting load and generation

II. PJM’s Clarifications Confirm that the Proposed Framework Does Not Preserve the

printed heading · Topic match: Reliability and curtailment

In particular, PJM confirms that, under Interim NITS, co-located load “will not have rights to the capacity/energy from any specific co-located generation” and that such generation is treated as part of the “network” resource pool rather than as a dedicated supply resource for the co-located load.5…
Read this passage Filed comments: Reliability and curtailment

III. The Proposal Unnecessarily Restricts the Use of Non-Firm Service and Precludes

printed heading · Topic match: Connecting load and generation

PJM’s stakeholder materials confirm that Non-Firm CDS is limited to use when the co-located generator is unavailable and must be requested in advance, with load consumption from the grid limited to approved firm and non-firm service levels.7 PJM further illustrates that where a customer is not…
Read this passage Filed comments: Connecting load and generation

IV. The Proposal Does Not Provide a Workable Pathway for Phased Development or

printed heading

The Proposal Does Not Provide a Workable Pathway for Phased Development or Load Ramping The proposed framework also fails to accommodate the phased and incremental development that characterizes large load projects.
Read this passage

V. Curtailment Risk and Operational Parameters Remain Insufficiently Defined

printed heading · Topic match: Reliability and curtailment

Moreover, PJM acknowledges that existing systems do not fully support the granularity required to implement certain aspects of the proposed services, which may necessitate additional operational workarounds or infrastructure.10 At the same time, PJM proposes an extremely stringent penalty framework…
Read this passage Filed comments: Reliability and curtailment

VI. The Proposal is Materially Incomplete and Relies on Future Developments

printed heading

The Proposal is Materially Incomplete and Relies on Future Developments DCC is also concerned that the proposed framework leaves numerous critical elements undefined or deferred.
Read this passage

VII. The Proposed Implementation Timeline Warrants Refinement

printed heading

The Proposed Implementation Timeline Warrants Refinement PJM proposes an implementation timeline extending to mid-2029, citing, among other considerations, capacity market alignment and system development needs (see PJM Initial Brief).
Read this passage

VIII. Conclusion

printed heading · Topic match: Connecting load and generation

However, those clarifications also highlight fundamental issues that must be addressed to ensure that the framework is workable in practice.
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, DC this 25th day of March 2026. /s/ Lucas Fykes Lucas Fykes Senior Director, Energy Policy & Regulatory Counsel Data Center Coalition 1250 H Street, NW, Suite 880 Washington, DC, 20005 lucas@datacentercoalition.org 13