Response Brief of Geronimo Power, LLC
Text extracted from the eLibrary original (SHA-256 51da403addc048ce…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
EL25-20-000 (Consolidated) RESPONSE BRIEF OF GERONIMO POWER, LLC Pursuant to the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) December 18, 2025 order1 and the Commission’s January 23, 2026 Notice of Extension of Time,2 Geronimo Power, LLC (“Geronimo Power”) hereby submits this…Read this passage Filed comments: Filing procedure
I. INTRODUCTION
printed heading · Topic match: Cost allocation
The Commission’s recognition that the PJM tariff must include transmission service offerings that reflect the use of the grid by co-located loads will, if properly implemented, ensure that co-located loads can come online more quickly and avoid triggering unnecessary transmission infrastructure…Read this passage Filed comments: Cost allocation
II. THE RATES PROPOSED BY THE PJM TRANSMISSION OWNERS ARE NOT
printed heading
THE RATES PROPOSED BY THE PJM TRANSMISSION OWNERS ARE NOT JUST AND REASONABLERead this passage
A. The PJM Transmission Owners Have Not Demonstrated That It Is Just And
printed heading · Topic match: Connecting load and generation
PJM has proposed that Non-Firm Contract Demand transmission service may only be taken up to the MW level that a co-located generation resource is able to supply a co-located load; the portion of load that is not supplied by co-located generation must take Firm Contract Demand transmission service.Read this passage Filed comments: Connecting load and generation
B. Any Grid Reliance Charge Must Be Based On Demonstrated System Benefits
printed heading · Topic match: Connecting load and generation
Any Grid Reliance Charge Must Be Based On Demonstrated System Benefits Any charges imposed on co-located loads must be based on co-located load’s actual impact on the grid and the transmission services they receive.Read this passage Filed comments: Connecting load and generation
III. CONCLUSION
printed heading
CONCLUSION Geronimo Power respectfully requests that the Commission issue an order in this proceeding consistent with this brief.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 25th day of March 2026. /s/ Stephen J.Read this passage