Reply Brief of the Independent Market Monitor in response to PJM Interconnection, L.L.C.’s initial brief filed on 02/23/2026
Text extracted from the eLibrary original (SHA-256 b8724074f90d2509…). Download the original from the official source.
Contents · 6 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al.Read this passage
I. REPLY BRIEF
printed heading
I.Read this passage
A. PJM Transmission Service
printed heading
PJM Transmission Service PJM’s brief includes key statements that should inform thinking about the proposed types of transmission service that the Commission identified in the December 18th Order.Read this passage
B. Contract Demand Service (CDS)
printed heading · Topic match: Connecting load and generation
ER26-1088-000 (February 25, 2026). 5 See December 18th Order at P 160. 5 any portion of the gross demand of the Co-Located Load not served by the Co-Located Generating Facility must be covered by firm contract demand transmission service.Read this passage Filed comments: Connecting load and generation
C. Interim NITS
printed heading · Topic match: Connecting load and generation
Interim NITS Interim NITS was created by the Commission in response to requests by large data center loads to interconnect more quickly than could occur for full NITS.Read this passage Filed comments: Connecting load and generation
D. Implementation Date
printed heading · Topic match: Connecting load and generation
For example, PJM points out (at 66) that “Eligible Customers taking transmission service on behalf of Co-Located Load, would need to take these different forms of transmission service on different feeders, or cables leaving substations, to ultimately serve the Co-Located Load.” 9Read this passage Filed comments: Connecting load and generation
II. CONCLUSION
printed heading
CONCLUSION The Market Monitor respectfully requests that the Commission afford due consideration to this reply brief as the Commission resolves the issues raised in this proceeding.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Eagleville, Pennsylvania, this 25th day of March, 2026.Read this passage