EL25-49-000 · 2026-03-26 · Monitoring Analytics, LLC

Reply Brief of the Independent Market Monitor in response to PJM Interconnection, L.L.C.’s initial brief filed on 02/23/2026

Text extracted from the eLibrary original (SHA-256 b8724074f90d2509…). Download the original from the official source.

Contents · 6 sections
  1. I. REPLY BRIEF p. 2
  2. A. PJM Transmission Service p. 2
  3. B. Contract Demand Service (CDS) p. 3
  4. C. Interim NITS p. 6
  5. D. Implementation Date p. 8
  6. II. CONCLUSION p. 9

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al.
Read this passage

I. REPLY BRIEF

printed heading

I.
Read this passage

A. PJM Transmission Service

printed heading

PJM Transmission Service PJM’s brief includes key statements that should inform thinking about the proposed types of transmission service that the Commission identified in the December 18th Order.
Read this passage

B. Contract Demand Service (CDS)

printed heading · Topic match: Connecting load and generation

ER26-1088-000 (February 25, 2026). 5 See December 18th Order at P 160. 5 any portion of the gross demand of the Co-Located Load not served by the Co-Located Generating Facility must be covered by firm contract demand transmission service.
Read this passage Filed comments: Connecting load and generation

C. Interim NITS

printed heading · Topic match: Connecting load and generation

Interim NITS Interim NITS was created by the Commission in response to requests by large data center loads to interconnect more quickly than could occur for full NITS.
Read this passage Filed comments: Connecting load and generation

D. Implementation Date

printed heading · Topic match: Connecting load and generation

For example, PJM points out (at 66) that “Eligible Customers taking transmission service on behalf of Co-Located Load, would need to take these different forms of transmission service on different feeders, or cables leaving substations, to ultimately serve the Co-Located Load.” 9
Read this passage Filed comments: Connecting load and generation

II. CONCLUSION

printed heading

CONCLUSION The Market Monitor respectfully requests that the Commission afford due consideration to this reply brief as the Commission resolves the issues raised in this proceeding.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Eagleville, Pennsylvania, this 25th day of March, 2026.