EL25-49-000 · 2026-04-24 · PJM Interconnection, L.L.C.

Reply Brief of PJM Interconnection, L.L.C

Text extracted from the eLibrary original (SHA-256 8558c8942d2ef16f…). Download the original from the official source.

Contents · 25 sections
  1. B. Interim NITS Customers Should Not Be Allowed Access to Co-Located p. 3
  2. C. The Illustrative Tariff Properly Details How PJM Will Study Requests for p. 3
  3. D. Non-Monetary Penalties Are Just and Reasonable and Necessary to Support p. 3
  4. IV. ADDITIONAL ILLUSTRATIVE TARIFF LANGUAGE TO INTEGRATE NEW p. 4
  5. I. INTRODUCTION p. 7
  6. II. RESPONSE TO ISSUES RAISED IN REPLY BRIEFS p. 10
  7. A. Contract Demand Transmission Service p. 10
  8. B. Interim NITS Customers Should Not Be Allowed Access to Co-Located p. 20
  9. C. The Illustrative Tariff Properly Details How PJM Will Study Requests for p. 26
  10. D. Non-Monetary Penalties Are Just and Reasonable and Necessary to p. 43
  11. E. Effective Date p. 59
  12. F. Issues Beyond the Scope of This Proceeding p. 62
  13. III. REVISIONS TO ILLUSTRATIVE TARIFF FILED WITH INITIAL BRIEF p. 64
  14. IV. ADDITIONAL ILLUSTRATIVE TARIFF LANGUAGE TO INTEGRATE p. 68
  15. V. DOCUMENT ENCLOSED p. 70
  16. Attachment A: Redlines on Reply Brief to Illustrative Language for New p. 70
  17. VI. CONCLUSION p. 70
  18. Attachment A p. 71
  19. Attachment F-3A. PJMSettlement shall be the Counterparty to the Interim Network Integration p. 72
  20. Attachment F-3A, the transmission service provided to the Eligible Customer will automatically p. 72
  21. Attachment F-3A, or requests in writing that the Transmission Provider file a p. 73
  22. Attachment F-4, or requests in writing that the Transmission Provider file a p. 82
  23. Attachment F-4, consistent with Good Utility Practice and any additional requirements reasonably p. 85
  24. ATTACHMENT F-3A p. 94
  25. ATTACHMENT F-4 p. 101

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.
Read this passage

TABLE OF CONTENTS

printed heading

Provision of Non-Firm Contract Demand Transmission Service . 13
Read this passage

B. Interim NITS Customers Should Not Be Allowed Access to Co-Located

printed heading

B.
Read this passage

C. The Illustrative Tariff Properly Details How PJM Will Study Requests for

printed heading

The Illustrative Tariff Properly Details How PJM Will Study Requests for New Transmission Services and Determine the Level of Service that Can Be Reliably Provided ................................................................................ 22 1.
Read this passage

D. Non-Monetary Penalties Are Just and Reasonable and Necessary to Support

printed heading · Topic match: Connecting load and generation

Upon Commission setting the terms and conditions for the new transmission services, PJM can begin receiving requests for such services and studying applications ................................................ 55 2.
Read this passage Filed comments: Connecting load and generation

IV. ADDITIONAL ILLUSTRATIVE TARIFF LANGUAGE TO INTEGRATE NEW

printed heading · Topic match: Connecting load and generation

This approach offers flexibility to Eligible Customers to mix and match between Firm and Non-Firm Contract Demand Transmission Service when taking service on behalf of Co-Located Load, so long as the combination of the two services covers the entire gross demand of the Co-Located Load.
Read this passage Filed comments: Connecting load and generation

I. INTRODUCTION

printed heading

The Regional Transmission Organization must have exclusive authority for maintaining the short-term reliability of the grid that it operates.
Read this passage

II. RESPONSE TO ISSUES RAISED IN REPLY BRIEFS

printed heading

II.
Read this passage

A. Contract Demand Transmission Service

printed heading · Topic match: Connecting load and generation

This capability must be added to the Energy Management System to allow PJM to evaluate when to curtail Co-Located Load before implementing emergency procedures.
Read this passage Filed comments: Connecting load and generation

B. Interim NITS Customers Should Not Be Allowed Access to Co-Located

printed heading · Topic match: Connecting load and generation

One, as directed by the Show Cause Order, Interim NITS (as well as the Contract Demand Transmission Services) must be designed based on two key principles: (1) the services are designed to serve loads that are “willing and able to control their withdrawals from the transmission system;”51 and (2)…
Read this passage Filed comments: Connecting load and generation

C. The Illustrative Tariff Properly Details How PJM Will Study Requests for

printed heading · Topic match: Connecting load and generation

As discussed below, the Illustrative Tariff provisions appropriately detail PJM’s process, role, and standards for studying requests for these new transmission services to serve load.
Read this passage Filed comments: Connecting load and generation

D. Non-Monetary Penalties Are Just and Reasonable and Necessary to

printed heading · Topic match: Reliability and curtailment

The size and pace of large load integration give rise to heightened reliability risk that calls for non-monetary penalties in addition to financial penalties The cost of unreliability—whether measured in dollars, frequency of rolling blackouts, impacts on national security or economic development,…
Read this passage Filed comments: Reliability and curtailment

E. Effective Date

printed heading · Topic match: Connecting load and generation

Upon Commission setting the terms and conditions for the new transmission services, PJM can begin receiving requests for such services and studying applications Several entities complain that a June 1, 2029 effective date for the Illustrative Tariff would be unjust and unreasonable.174 In its…
Read this passage Filed comments: Connecting load and generation

F. Issues Beyond the Scope of This Proceeding

printed heading · Topic match: Connecting load and generation

First, the Show Cause Order did not direct PJM to alter the scope of its interconnection studies for generators, and therefore this claim is beyond the scope of this proceeding.186 Second, on the merits, to maintain system reliability, PJM must study all interconnecting generators—but the scope of…
Read this passage Filed comments: Connecting load and generation

III. REVISIONS TO ILLUSTRATIVE TARIFF FILED WITH INITIAL BRIEF

printed heading · Topic match: Connecting load and generation

Illustrative Tariff, Part XI, Subpart A – Interim Network Integration Transmission Service • Section 702.3: Consistent with the Show Cause Order’s holding that Interim NITS “would only be available to the extent PJM determines that it can provide some level of interim service reliably,”190 PJM has…
Read this passage Filed comments: Connecting load and generation

IV. ADDITIONAL ILLUSTRATIVE TARIFF LANGUAGE TO INTEGRATE

printed heading · Topic match: Connecting load and generation

ADDITIONAL ILLUSTRATIVE TARIFF LANGUAGE TO INTEGRATE NEW TRANSMISSION SERVICES AND RESERVATION OF RIGHTS TO FURTHER SUPPLEMENT FILING As PJM discussed in its Initial Brief, the addition of three new transmission services to offer new means for Eligible Customers to serve Co-Located Load, requires…
Read this passage Filed comments: Connecting load and generation

V. DOCUMENT ENCLOSED

printed heading

DOCUMENT ENCLOSED In addition to this reply brief, PJM encloses the following: 1.
Read this passage

Attachment A: Redlines on Reply Brief to Illustrative Language for New

printed heading

Attachment A: Redlines on Reply Brief to Illustrative Language for New Tariff, Part XI; Attachments F-3A and F-4; and Other Illustrative Tariff Revisions
Read this passage

VI. CONCLUSION

printed heading

CONCLUSION PJM respectfully requests that the Commission find that the Illustrative Tariff, as revised through this reply brief, forms part of a just and reasonable replacement rate in accordance with the requirements of the Show Cause Order.
Read this passage

Attachment A

printed heading

Attachment A Redlines on Reply Brief to Illustrative Language for New Tariff, Part XI; Attachments F-3A and F-4; and Other Illustrative Tariff Revisions 1 Tariff, Part XI Transmission Services Available for Eligible Customers Taking Service on Behalf of Co-Located Loads Subpart A – Interim Network…
Read this passage

Attachment F-3A. PJMSettlement shall be the Counterparty to the Interim Network Integration

printed heading · Topic match: Connecting load and generation

PJMSettlement shall be the Counterparty to the Interim Network Integration Transmission Service transactions under this Tariff.
Read this passage Filed comments: Connecting load and generation

Attachment F-3A, the transmission service provided to the Eligible Customer will automatically

printed heading · Topic match: Connecting load and generation

The Eligible Customer taking Interim Network Integration Transmission Service must obtain or provide Ancillary Services pursuant to Tariff, Part I, section 3. 2 701.2 Interim Network Integration Transmission Service The Transmission Provider may provide non-firm, interruptible transmission service…
Read this passage Filed comments: Connecting load and generation

Attachment F-3A, or requests in writing that the Transmission Provider file a

printed heading · Topic match: Connecting load and generation

An Eligible Customer with an effective Service Agreement will be eligible to obtain Non-Firm Contract Demand Transmission Service on a given Operating Day only to the extent the portion of the Co-Located Generating Facility dedicated to serving the Co-Located Load is on outage. (c) The cumulative…
Read this passage Filed comments: Connecting load and generation

Attachment F-4, or requests in writing that the Transmission Provider file a

printed heading · Topic match: Connecting load and generation

If requested by the Transmission Provider, an Application for Firm Contract Demand Transmission Service and/or Non-Firm Contract Demand Transmission Service shall provide all of the information included in 18 C.F.R. § 2.20, including but not limited to the following: (i) The identity, address,…
Read this passage Filed comments: Connecting load and generation

Attachment F-4, consistent with Good Utility Practice and any additional requirements reasonably

printed heading · Topic match: Connecting load and generation

The Co-Located Load shall be specified in the Service Agreement for Contract Demand Transmission Service, provided in Attachment F-4. (b) The Eligible Customer must designate the individual Co-Located Generating Facility that will serve the individual Co-Located Load in subsection (a) and provide…
Read this passage Filed comments: Connecting load and generation

ATTACHMENT F-3A

printed heading · Topic match: Connecting load and generation

ATTACHMENT F-3A Service Agreement For Regional Network Integration Transmission Service And/or Interim Network Integration Transmission Service (For Co-Located Load) 1.0 This Service Agreement, dated as of the date the last party executes this agreement, is entered into, by and between the Office…
Read this passage Filed comments: Connecting load and generation

ATTACHMENT F-4

printed heading · Topic match: Connecting load and generation

Office of the Interconnection: By: ______________________ _______________ ______________ Name Title Date Counterparty: By: ______________________ _______________ ______________ Name Title Date Eligible Customer: By: ______________________ _______________ ______________ Name Title Date 33…
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 24th day of April 2026. /s/ Ruth M.