Reply Brief of PJM Industrial Customer Coalition, et al
Text extracted from the eLibrary original (SHA-256 fcec260e010d0651…). Download the original from the official source.
Contents · 7 sections
- I. EXECUTIVE SUMMARY
- II. ARGUMENTS
- B. The Grid Reliance Charge Must Comport with Actual Use.
- C. The FERC Can Avoid Stressing the PJM Queue and Study Process and
- D. The Penalty Regime Should be Developed Cautiously.
- E. The Retail Threshold, Set Appropriately, Can Avoid Significant Customer
- III. CONCLUSION & REQUEST FOR RELIEF
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al.Read this passage
I. EXECUTIVE SUMMARY
printed heading · Topic match: Reliability and curtailment
Consistent with burgeoning efforts by policymakers to protect existing retail customers, the Commission must also protect traditional large users in accordance with FERC’s statutory mandate under the Federal Power Act (“FPA”), which requires that rates and terms of jurisdictional service be just,…Read this passage Filed comments: Reliability and curtailment
II. ARGUMENTS
printed heading · Topic match: Reliability and curtailment
The rate for sales of back-up power or maintenance power: (1) Shall not be based upon an assumption (unless supported by factual data) that forced outages or other reductions in electric output by all qualifying facilities on an electric utility's system will occur simultaneously, or during the…Read this passage Filed comments: Reliability and curtailment
B. The Grid Reliance Charge Must Comport with Actual Use.
printed heading · Topic match: Connecting load and generation
See also PJM Initial Brief at 16 (proposing that “[a]n Eligible Customer taking service on behalf of a Co-Located Load must request Non-Firm Contract Demand Transmission Service equivalent to the MW level of the Co-Located Generating Facility dedicated to serving the Co-Located Load”). 14…Read this passage Filed comments: Connecting load and generation
C. The FERC Can Avoid Stressing the PJM Queue and Study Process and
printed heading · Topic match: Connecting load and generation
While the FERC is pursuing major industry reforms in the Co-Located Load proceeding, the Industrials/Amtrak respectfully request that the Commission take care to accomplish the desired reforms without creating undue hardship for those impacted by the rule changes—namely, retail customers who have…Read this passage Filed comments: Connecting load and generation
D. The Penalty Regime Should be Developed Cautiously.
printed heading · Topic match: Connecting load and generation
If the Transmission Owners’ proposal is accepted, the mill owes a $1+ million annual charge for Non-Firm CDS (approximately 25% of the NITS cost) for its 80 MW on-site generation—but at least the mill avoids an increase of $4 million per year, which would occur under a regime that the customer must…Read this passage Filed comments: Connecting load and generation
E. The Retail Threshold, Set Appropriately, Can Avoid Significant Customer
printed heading · Topic match: Connecting load and generation
The Industrials/Amtrak fully support grid reliability and resource adequacy.Read this passage Filed comments: Connecting load and generation
III. CONCLUSION & REQUEST FOR RELIEF
printed heading · Topic match: Connecting load and generation
Specifically, the Industrials/Amtrak ask the Commission to implement the Co-Located Load Order in a measured and careful fashion that does not result in adverse cost consequences to traditional large users, including manufacturers and transportation customers.Read this passage Filed comments: Connecting load and generation
CERTIFICATE OF SERVICE
printed heading
Dated this 24th day of April, 2026. /s/ Matthew L.Read this passage