Petition for Review filed in the U.S. Court of Appeals for the District of Columbia Circuit of American Transmission Systems, Incorporated, et al. re…
Text extracted from the eLibrary original (SHA-256 0a16be2a04786d44…). Download the original from the official source.
Contents · 25 sections
- ATTACHMENT A
- I. Background
- A. Show Cause Order
- B. Behind the Meter Generation
- C. Eligible Customer
- II. PJM's Answer to Show Cause Order and Responsive Pleadings"
- A. PJM's Options for Co-Location Arrangements
- B. General
- C. Jurisdiction
- D. Cost Allocation
- E. Interconnection Procedures and Cost Allocation
- Attachment M-3 was designed for supplemental transmission projects, not load
- F. PJM Capacity Market Reliability. and Resource Adequacy
- G. Other Arguments
- III. Notice of Show Cause Proceeding and Responsive Pleadings
- IV. Discussion
- A. Procedural Matters
- B. Substantive Matters
- Conclusion
- ATTACHMENT B
- ATTACHMENT C: SERVICE LIST
- F. Alvin Taylor
- F. Alvin Taylor
- F. Alvin Taylor
- F. Alvin Taylor
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
PJM Interconnection, L.L.C., Notice of Denial of Rehearing By Operation of Law and Providing for Further Consideration, 194 FERC ¶ 62,089, Docket Nos.Read this passage Filed comments: Filing procedure
CERTIFICATE OF SERVICE
printed heading
Reese, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Robert Solomon, Solicitor Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 and by email on all parties on the Commission's service lists for Docket Nos.Read this passage
ATTACHMENT A
printed heading · Topic match: Connecting load and generation
We also direct PJM to file, within 30 days of the date of issuance of this order, a compliance filing to revise its Tariff to make clear how Interconnection Customers can make use of provisional interconnection service, the ability to request interconnection service below nameplate capacity, the…Read this passage Filed comments: Connecting load and generation
I. Background
printed heading
I.Read this passage
A. Show Cause Order
printed heading · Topic match: Connecting load and generation
EL25-49-000, et al. 7 Commission stated that, while both Co-Located Load and non-co-located load may have similar resource adequacy impacts, the speed at which Co-Located Load can be added to the grid may pose particular resource adequacy challenges, especially if Co-Location Arrangements are not…Read this passage Filed comments: Connecting load and generation
B. Behind the Meter Generation
printed heading
Transmission rates for NITS and Point-to-Point Service (PTPS) are based on transmission formula rates filed by the transmission owners.Read this passage
C. Eligible Customer
printed heading · Topic match: Cost allocation
This definition forms the basis for PJM's existing transmission cost allocation approach, through which each Eligible Customer is billed for the charges associated with the transmission services used to serve its load. 28 PJM, Intra-PJM Tariffs, OATT, § I.1 Defmitions - E-F (41.0.0) (defining…Read this passage Filed comments: Cost allocation
II. PJM's Answer to Show Cause Order and Responsive Pleadings"
printed heading
PJM's Answer to Show Cause Order and Responsive Pleadings"Read this passage
A. PJM's Options for Co-Location Arrangements
printed heading · Topic match: Connecting load and generation
PJM requests that, if "the record supports consideration of additional options," the Commission issue detailed guiding principles that PJM can operationalize in an FPA section 205 filing.31 13.Read this passage Filed comments: Connecting load and generation
B. General
printed heading · Topic match: Connecting load and generation
According to Indicated Transmission Owners, all load in PJM must be designated as Network Load and served by a Network Customer (or take PTPS), thereby ensuring this load pays its fair share of transmission costs.Read this passage Filed comments: Connecting load and generation
C. Jurisdiction
printed heading · Topic match: Connecting load and generation
Several parties support the Commission's exercise of jurisdiction over the taking of transmission service.67 Market Monitor and UCS argue that Co-Location Arrangements are interconnected to the transmission grid and receive jurisdictional service from jurisdictional transmission facilities.68 CATF…Read this passage Filed comments: Connecting load and generation
D. Cost Allocation
printed heading · Topic match: Connecting load and generation
Indicated Transmission Owners suggest that adding a definition of Co-Located Load to the PJM Tariff specifying that co-located must be either Network Load or served by PTPS and does not meet the definition of BTMG may clarify expectations and obligations associated with such load."' Indicated…Read this passage Filed comments: Connecting load and generation
E. Interconnection Procedures and Cost Allocation
printed heading · Topic match: Connecting load and generation
Bloom proposes an alternative to PJM's option 6 to adopt reforms to interconnect generation and Co-Located Load (both new) as a composite facility called an "energy park," instead of studying the load in one process and the generation in another.224 106.Read this passage Filed comments: Connecting load and generation
Attachment M-3 was designed for supplemental transmission projects, not load
printed heading · Topic match: Cost allocation
Attachment M-3 was designed for supplemental transmission projects, not load interconnection, and is not suitable for large load interconnection.249 EDFR asks the Commission to provide guidance to PJM and other Regional Transmission Organization or Independent System Operator (RTO/ISO) and…Read this passage Filed comments: Cost allocation
F. PJM Capacity Market Reliability. and Resource Adequacy
printed heading · Topic match: Connecting load and generation
Market Monitor argues that there should be no artificial incentives or changes to fundamental capacity market rules that allow preferential treatment of large loads.274 OPSI states that Capacity Resources cannot prioritize serving non-PJM load, even as backup, without undermining system reliability…Read this passage Filed comments: Connecting load and generation
G. Other Arguments
printed heading · Topic match: Cost allocation
A number of parties urge that any Commission action in this proceeding provide flexibility for different regions325 and/or different co-location configurations.326 California Utilities request that the Commission recognize that approaches to co-located facilities must be tailored to account for…Read this passage Filed comments: Cost allocation
III. Notice of Show Cause Proceeding and Responsive Pleadings
printed heading · Topic match: Connecting load and generation
On September 19, 2025, a letter from then-Chairman Rosner to PJM was filed in this proceeding; then-Chairman Rosner's letter requests information on load forecasting.Read this passage Filed comments: Connecting load and generation
IV. Discussion
printed heading
IV.Read this passage
A. Procedural Matters
printed heading
Pursuant to Rule 214(d) of the Commission's Rules of Practice and Procedure, 18 C.F.R. § 385.214(d), we grant the late-filed motions to intervene given these entities' interests in the proceeding, the early stage of the proceeding, and the absence of undue prejudice or delay. 158.Read this passage
B. Substantive Matters
printed heading · Topic match: Connecting load and generation
As the Commission explained in Order No. 845, Interconnection Customers may seek provisional interconnection service when available studies or additional studies as necessary indicate that there is a level of interconnection service that can occur without any additional Interconnection Facilities…Read this passage Filed comments: Connecting load and generation
Conclusion
printed heading · Topic match: Cost allocation
As we establish new transmission services, it cannot come at the expense of other ratepayers.Read this passage Filed comments: Cost allocation
ATTACHMENT B
printed heading · Topic match: Filing procedure
As provided in 16 U.S.C. § 8251(a), the requests for rehearing of the above-cited order filed in this proceeding will be addressed in a future order to be issued consistent with the requirements of such section.Read this passage Filed comments: Filing procedure
ATTACHMENT C: SERVICE LIST
printed heading
ATTACHMENT C: SERVICE LIST Andrew Hinz Andrew Hinz 1427 PARK AVE BALTIMORE, MARYLAND 21217 UNITED STATES ahinz61@outlook.com Advanced Energy United Michael Haugh Policy Director Advanced Energy United 1010 VERMONT AVE NW WASHINGTON, DISTRICT OF COLUMBIA 20005 UNITED STATES…Read this passage
F. Alvin Taylor
printed heading
Alvin Taylor Attorney McCarter & English, LLP 1301 K Street, NW Suite 1000 West Washington, DISTRICT OF COLUMBIA 20005 UNITED STATES ataylor@mccarter.com EDF Renewables, Inc.Read this passage
F. Alvin Taylor
printed heading
Alvin Taylor Attorney McCarter & English, LLP 1301 K Street, NW Suite 1000 West Washington, DISTRICT OF COLUMBIA 20005 ataylor@mccarter.com Lee County Electric Cooperative, Inc.Read this passage
F. Alvin Taylor
printed heading · Topic match: Registry access
Gregory Carmean Executive Director Organization of PJM States, Inc. 700 Barksdale Road Suite 1 Newark, DELAWARE 19711 UNITED STATES greg@opsi.us Pacific Gas and Electric Company Charles Middlekauff Chief Counsel Pacific Gas and Electric Company PO Box 1018 Oakland,CALIFORNIA 94604-1018 UNITED…Read this passage Filed comments: Registry access
F. Alvin Taylor
printed heading
Alvin Taylor Attorney 1301 K Street, NW Suite 1000 West Washington, DISTRICT OF COLUMBIA 20005 UNITED STATES ataylor@mccarter.com Randolph L.Read this passage