ER26-1479-000 · 2026-05-08 · PJM Industrial Customer Coalition, Industrial Energy Consumers of AmericaAmerican Forest and Paper Association, Inc., National Railroad Passenger Corporation ("Amtrak")

Motion for Leave to Answer and Limited Answer of PJM Industrial Customer Coalition et al. to the Indicated PJM Transmission Owners’ 04/24/2026 Motion for…

Text extracted from the eLibrary original (SHA-256 239f1c15db866188…). Download the original from the official source.

Contents · 6 sections
  1. I. MOTION FOR LEAVE TO ANSWER p. 1
  2. II. LIMITED ANSWER p. 2
  3. A. The Transmission Owners’ discussion of the Retail Threshold fails to address p. 2
  4. B. The Retail Threshold should be based on load, not generator size. p. 4
  5. C. Regulatory certainty and legally durable rules are essential for investment. p. 6
  6. III. CONCLUSION & REQUEST FOR RELIEF p. 8

Read topic-matched comments in ER26-1479

Topics in the text: Connecting load and generation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) ) ) ) Docket No.
Read this passage

I. MOTION FOR LEAVE TO ANSWER

printed heading · Topic match: Connecting load and generation

The Answer was filed on April 24, 2026, in response to various protests and comments on PJM Interconnection, L.L.C.’s (“PJM”) 60-Day Compliance Filing in the above-captioned proceeding. 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access Transmission Tariff to Comply with…
Read this passage Filed comments: Connecting load and generation

II. LIMITED ANSWER

printed heading

II.
Read this passage

A. The Transmission Owners’ discussion of the Retail Threshold fails to address

printed heading

Actual use should remain the operative principle, with the caveat that certain considerations must be made for loads that create substantial 7 April 24 Motion/Answer at 2. 8 Industrials/Amtrak Protest at 14-15. 4 reliability risk.
Read this passage

B. The Retail Threshold should be based on load, not generator size.

printed heading · Topic match: Reliability and curtailment

EL25-49-000, EL25-49-001, AD24-11-000, EL25-20-000 (“Consolidated Dockets”) (Dec. 18, 2025) (“Order”). 5 and resource adequacy risks posed by large Retail BTMG, while allowing smaller customers to continue netting in a transparent and not unduly discriminatory manner.”11 However, this argument…
Read this passage Filed comments: Reliability and curtailment

C. Regulatory certainty and legally durable rules are essential for investment.

printed heading · Topic match: Connecting load and generation

Over-reliance on grandfathering rules will make this process more daunting for decision makers who must be accountable to their shareholders and stakeholders.
Read this passage Filed comments: Connecting load and generation

III. CONCLUSION & REQUEST FOR RELIEF

printed heading

CONCLUSION & REQUEST FOR RELIEF The Industrials/Amtrak respectfully request that the Commission accept their Limited Answer above; reject PJM’s Compliance Filing, consistent with their Protest and Comments filed on March 16, 2026; and direct PJM to file a new compliance filing, consistent with the…
Read this passage

CERTIFICATE OF SERVICE

printed heading

Garber 100 Pine Street Harrisburg, PA 17101 Tel: 717-232-8000 Fax: 717-237-5433 E-mail: mgarber@mcneeslaw.com