PJM Interconnection, L.L.C. submits third supplemental Informational Report re timeline for stakeholder deliberation on the reliability backstop procurement…
Text extracted from the eLibrary original (SHA-256 252485f01ff9d064…). Download the original from the official source.
Contents · 3 sections
Read topic-matched comments in EL25-49
Topics in the text: Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
PJM Interconnection, L.L.C. 2750 Monroe Blvd Audubon, PA 19403 Daniel Vinnik Counsel T: (267) 858-9451 Daniel.Vinnik@pjm.com May 20, 2026 Honorable Debbie-Anne A.Read this passage
I. INFORMATIONAL FILING
printed heading
INFORMATIONAL FILING Since the March 9, 2026 second supplemental informational report, PJM has continued to discuss the framework of a reliability backstop procurement mechanism with stakeholders.Read this passage
II. CONCLUSION
printed heading
CONCLUSION PJM pledges to keep the Commission informed of the timeline for submission of a filing to the Commission if changes to the current timeline become necessary.Read this passage
CERTIFICATE OF SERVICE
printed heading
CERTIFICATE OF SERVICE I hereby certify that I have this 20th day of May, 2026 caused a copy of the foregoing document to be served upon each person designated on the official service list compiled by the Secretary in this proceeding. /s/ Daniel Vinnik Daniel Vinnik Counsel PJM Interconnection,…Read this passage
Attachment A
printed heading · Topic match: Filing procedure
Accelerating the centralized procurement recognizes that certainty in C&M is necessary to better support bilateral transactions, but that final certainty, recognizing the potential for rehearing requests and court challenge, may not be available until sometime in 2027.Read this passage Filed comments: Filing procedure