Prefiled Statement for Panelists from PJM Interconnection, L.L.C., for the PJM Governance and Stakeholder Reforms Technical Conference
Text extracted from the eLibrary original (SHA-256 4daaea7b58fc126b…). Download the original from the official source.
Contents · 7 sections
- I. Introduction and Summary
- II. PJM's Mission and the Regional Challenge
- III. The Stakeholder Process Works Well in Many Cases, But Matters of
- IV. Any Governance Reform Should Strengthen PJM's Ability To Act
- V. Any Stakeholder Reform Should Preserve Participation and Improve
- VI. Enhancements to the State Role in PJM Governance
- VII. Next Steps
Read topic-matched comments in AD26-7
Topics in the text: Reliability and curtailment · Registry access · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
For Public Use Comments from PJM Interconnection, L.L.C.Read this passage
I. Introduction and Summary
printed heading
It must therefore be able to not only incorporate diverse stakeholder input, but also act with greater speed, clarity and decisiveness in bringing well- developed proposals before this Commission.Read this passage
II. PJM's Mission and the Regional Challenge
printed heading
PJM's Mission and the Regional Challenge PJM's Operating Agreement establishes the Board's governing principles, including the safe and reliable operation of the bulk electric grid in the PJM region; the creation and operation of a robust, competitive and nondiscriminatory electric power market;…Read this passage
III. The Stakeholder Process Works Well in Many Cases, But Matters of
printed heading · Topic match: Registry access
The process includes, and benefits from, many perspectives: residential ratepayers, consumer advocates, states, utilities, generators, suppliers, developers, large customers and other stakeholders.Read this passage Filed comments: Registry access
IV. Any Governance Reform Should Strengthen PJM's Ability To Act
printed heading
The Commission must act within 60 days of the filing, or the filing is deemed accepted.Read this passage
V. Any Stakeholder Reform Should Preserve Participation and Improve
printed heading · Topic match: Reliability and curtailment
For issues that materially affect reliability, market performance, resource adequacy, large load integration or transmission planning, etc., PJM and its stakeholder body should enforce defined timelines for issue identification, options development, stakeholder comment, voting and escalation.Read this passage Filed comments: Reliability and curtailment
VI. Enhancements to the State Role in PJM Governance
printed heading · Topic match: Reliability and curtailment
Such changes included a “must-offer” requirement for all resources in the capacity market, the inclusion of Reliability Must-Run resources in the market and the pricing cap/floor proposal.Read this passage Filed comments: Reliability and curtailment
VII. Next Steps
printed heading
Next Steps PJM appreciates the Commission holding this Technical Conference and outlines below possible options for moving forward.Read this passage