ER26-1479-001 · 2026-07-20 · Constellation Energy Generation, LLC

Constellation Energy Generation, LLC submits Limited Request for Rehearing and Clarification of the 06/18/2026 Order

Text extracted from the eLibrary original (SHA-256 f9bbbde036ea6e81…). Download the original from the official source.

Contents · 6 sections
  1. I. The Commission Should Require Study Deadlines Binding Both PJM and the p. 4
  2. II. The Commission Should Direct PJM to Clarify its Necessary Study Process in its Tariff p. 8
  3. IV. Transmission Owners Should Not Have Unfettered Discretion over Necessary Control p. 13
  4. I. The Commission Should Direct PJM to Revise the Definition of Co-Located Generating p. 15
  5. II. An Applicant with a Pending NITS Application Should Be Allowed to Request Interim p. 16
  6. CONCLUSION p. 18

Read topic-matched comments in ER26-1479

Topics in the text: Connecting load and generation · Filing procedure · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

ER26-1479-000 LIMITED REQUEST FOR REHEARING AND CLARIFICATION OF CONSTELLATION ENERGY GENERATION, LLC Constellation submits this limited request for rehearing and clarification of the June 2026 Co-Location Order.1 We raise four discrete points on rehearing to reinforce the Commission’s objective of…
Read this passage Filed comments: Filing procedure

I. The Commission Should Require Study Deadlines Binding Both PJM and the

printed heading · Topic match: Retail and wholesale authority

New transmission service requests will be subject to the same delays unless the Commission requires PJM to establish and enforce deadlines that bind both PJM and the Transmission Owners. insisting that Constellation or its potential customer must first apply for retail service and designate what…
Read this passage Filed comments: Retail and wholesale authority

II. The Commission Should Direct PJM to Clarify its Necessary Study Process in its Tariff

printed heading · Topic match: Reliability and curtailment

PP 523-24. 42 See NEPGA, 881 F.3d at 211 (finding “that FERC did not engage in the reasoned decisionmaking required by the Administrative Procedure Act” because it “failed to respond to the substantial arguments put forward by Petitioners and failed to square its decision with its past precedent”)…
Read this passage Filed comments: Reliability and curtailment

IV. Transmission Owners Should Not Have Unfettered Discretion over Necessary Control

printed heading · Topic match: Connecting load and generation

Simply stated, Transmission Owners do not favor Co-located Load arrangements and have delayed their implementation when given the opportunity to do so.47 As a result, Transmission Owner review of necessary control technologies and/or protections systems should be consistent with Good Utility…
Read this passage Filed comments: Connecting load and generation

I. The Commission Should Direct PJM to Revise the Definition of Co-Located Generating

printed heading · Topic match: Connecting load and generation

This is because PJM defines “Generating Facility” as meaning a “Project Developer’s device for the production and/or storage for later injection of electricity” which “consists of one or more generating unit(s) and/or storage device(s).”54 It is unclear how the June 2026 Co-Location Order’s…
Read this passage Filed comments: Connecting load and generation

II. An Applicant with a Pending NITS Application Should Be Allowed to Request Interim

printed heading

Accordingly, Constellation requests that the Commission direct PJM to clarify that an Interim NITS request can be added to a pending NITS application without causing the applicant to restart or delay the NITS process.
Read this passage

CONCLUSION

printed heading · Topic match: Filing procedure

CONCLUSION For the reasons set forth above, Constellation respectfully requests that the Commission grant rehearing and clarification of the June 2026 Co-Location Order.
Read this passage Filed comments: Filing procedure

CERTIFICATE OF SERVICE

printed heading

CERTIFICATE OF SERVICE I hereby certify that I have on this 20th day of July, 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §…