The PJM Industrial Customer Coalition, et al. submit Request for Rehearing and Clarification of the 06/18/2026 Order
Text extracted from the eLibrary original (SHA-256 9c2935ea9940c913…). Download the original from the official source.
Contents · 7 sections
Read topic-matched comments in ER26-1479
Topics in the text: Filing procedure · Reliability and curtailment · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
EL25-49-002 EL25-49-000 AD24-11-001 EL25-20-001 (Consolidated) ER26-1479-000 REQUEST FOR REHEARING AND CLARIFICATION OF THE INDUSTRIAL CUSTOMERS/AMTRAK Pursuant to Rule 713 of the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) Rules of Practice and Procedure,1 the PJM Industrial…Read this passage Filed comments: Filing procedure
I. INTRODUCTION
printed heading · Topic match: Filing procedure
Dauphinais further demonstrated why PURPA QFs should be eligible for retail netting for their full load and emphasized that the FERC’s longstanding regulations governing rates for sales of back-up power or maintenance power to QFs must not be ignored, given that transmission is a key component of…Read this passage Filed comments: Filing procedure
II. BACKGROUND ON INDUSTRIALS AND AMTRAK
printed heading
BACKGROUND ON INDUSTRIALS AND AMTRAK The Industrials include associations of leading American manufacturing companies, trade- exposed electricity users, institutional users, and other energy-intensive customers, including hospitals, universities, and educational institutions.Read this passage
III. RESERVATION OF APPELLATE RIGHTS
printed heading · Topic match: Filing procedure
Accordingly, any decision not to re-litigate or re-challenge issues that are already pending before the Third Circuit shall not constitute waiver or failure to exhaust administrative remedies.Read this passage Filed comments: Filing procedure
IV. REQUEST FOR REHEARING
printed heading · Topic match: Filing procedure
REQUEST FOR REHEARINGRead this passage Filed comments: Filing procedure
A. STATEMENT OF ISSUES/SPECIFICATION OF ERRORS
printed heading · Topic match: Cost allocation
Due to the specific errors identified herein and the lack of a record upon which to base these determinations, the June Order should be modified on rehearing if any of the Clarifications requested herein are not granted.Read this passage Filed comments: Cost allocation
B. ARGUMENT
printed heading · Topic match: Reliability and curtailment
ARGUMENT In the December Order and June Order, the Commission cites changing circumstances on the transmission grid regarding reliability and resource adequacy risks as the underpinning reason that BTMG rules must change.28 The expansive growth of super-sized computational load has driven the need…Read this passage Filed comments: Reliability and curtailment
V. CONCLUSION
printed heading · Topic match: Filing procedure
CONCLUSION WHEREFORE, the Industrials/Amtrak respectfully request that the Commission grant rehearing of the June Order for the reasons set forth herein.Read this passage Filed comments: Filing procedure
CERTIFICATE OF SERVICE
printed heading
Dated this 20th day of July, 2026. /s/ Matthew L.Read this passage