Motion for Extension of Time for Specified Compliance Requirements and Request for Expedited Treatment of PJM Interconnection, L.L.C
Text extracted from the eLibrary original (SHA-256 6ba8341a67967cf1…). Download the original from the official source.
Contents · 8 sections
Read topic-matched comments in EL25-49
Topics in the text: Filing procedure · Connecting load and generation · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
PJM requests the Commission grant expedited treatment to act on this motion within ten days, by August 6, 2026, in the interest of regulatory certainty. 4 16 U.S.C. § 824d. 5 PJM Interconnection, L.L.C., Motion of PJM Interconnection, L.L.C. to Hold Proceeding in Abeyance and Request for Shortened…Read this passage Filed comments: Filing procedure
I. BACKGROUND
printed heading
I.Read this passage
A. Co-Located Load Proceeding
printed heading · Topic match: Connecting load and generation
Co-Located Load Proceeding The Commission initiated this proceeding on December 18, 2025.6 Following multiple compliance filings and paper hearing submissions, the Commission issued the Compliance Order on June 18, 2026 accepting most of PJM’s proposed Tariff changes, but directing PJM to make a…Read this passage Filed comments: Connecting load and generation
B. Large Load Proceeding
printed heading · Topic match: Cost allocation
Large Load Proceeding Also on June 18, 2026, the Commission initiated a new show cause proceeding via the Large Load Order.11 The Large Load Order found that several aspects of PJM’s Tariff appeared unjust and unreasonable due to the lack of specific procedures for integrating large loads,…Read this passage Filed comments: Cost allocation
C. Overlap Between Proceedings
printed heading · Topic match: Connecting load and generation
Third, the Compliance Order directed PJM to revise the Tariff to provide additional detail regarding the operational requirements and necessary control technologies to be 19 Compliance Order at P 91 (directing PJM to expand new transmission services to customers serving those with BTMG that are…Read this passage Filed comments: Connecting load and generation
D. Compliance Plan
printed heading · Topic match: Connecting load and generation
PJM has or will be scheduling stakeholder engagement sessions to both share and receive feedback on PJM’s proposal (including aspects of the co-located load compliance filing) on July 30, 2026, August 18, 2026, and September 16, 2026.26 PJM proposes to submit its remaining compliance filing in this…Read this passage Filed comments: Connecting load and generation
II. MOTION FOR EXTENSION OF TIME
printed heading · Topic match: Connecting load and generation
As noted above, both orders require PJM to propose Tariff changes to address the study procedures to interconnect Co-Located/Large Loads, make new transmission services available for customers that are willing and able to limit their withdrawals, and specify operational 27 See 18 C.F.R. § 385.2008.…Read this passage Filed comments: Connecting load and generation
III. REQUEST FOR EXPEDITED TREATMENT
printed heading · Topic match: Filing procedure
REQUEST FOR EXPEDITED TREATMENT PJM respectfully requests that the Commission consider this motion on an expedited basis to act on this request within ten days of filing, by August 6, 2026.Read this passage Filed comments: Filing procedure
IV. CONCLUSION
printed heading · Topic match: Filing procedure
CONCLUSION For the reasons stated above, PJM requests the Commission (i) grant a ninety-day extension of time for the specified compliance obligations in the Compliance Order and (ii) expeditiously act on this motion within ten days, by August 6, 2026.Read this passage Filed comments: Filing procedure
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, DC, this 28th day of July 2026. /s/ Ruth M.Read this passage