AD26-7-000 · 2026-08-03 · Individual No Affiliation

Post-Conference Comments of Persistence Analytics Group LLC re the PJM Governance and Stakeholder Reforms

Text extracted from the eLibrary original (SHA-256 e5967fee79e79837…). Download the original from the official source.

Contents · 7 sections
  1. I. THE COMMISSION SHOULD DEFINE THE OUTCOME BEFORE REFORMING THE p. 3
  2. II. PJM MUST CREATE A FORMAL ASSUMPTION-ACCOUNTABILITY RECORD p. 3
  3. III. LARGE-LOAD FORECASTS REQUIRE DECISION-GRADE CLASSIFICATION p. 3
  4. IV. COST CAUSATION MUST FOLLOW THE FULL ELECTRICAL CONSEQUENCE p. 4
  5. V. MATERIAL EVIDENTIARY CHALLENGES NEED INDEPENDENT ESCALATION p. 4
  6. VI. THE SEPTEMBER DISPUTE-RESOLUTION PROCESS MUST END WITH p. 4
  7. VII. CONCLUSION p. 5

Read topic-matched comments in AD26-7

Topics in the text: Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

Osnato, Founder Date August 3, 2026 GOVERNANCE MUST PRODUCE ACCOUNTABILITY.
Read this passage Filed comments: Cost allocation

I. THE COMMISSION SHOULD DEFINE THE OUTCOME BEFORE REFORMING THE

printed heading

THE COMMISSION SHOULD DEFINE THE OUTCOME BEFORE REFORMING THE PROCESS The purpose of PJM governance is not stakeholder participation for its own sake.
Read this passage

II. PJM MUST CREATE A FORMAL ASSUMPTION-ACCOUNTABILITY RECORD

printed heading

PJM MUST CREATE A FORMAL ASSUMPTION-ACCOUNTABILITY RECORD For each material planning, market, procurement, or cost-allocation decision, PJM should publish a concise assumption-accountability record identifying: • The decision owner: the PJM officer or committee accountable for the final…
Read this passage

III. LARGE-LOAD FORECASTS REQUIRE DECISION-GRADE CLASSIFICATION

printed heading · Topic match: Reliability and curtailment

Operationally durable The expected operating profile, persistence, ramp behavior, curtailment capability, and withdrawal risk have been evaluated.
Read this passage Filed comments: Reliability and curtailment

IV. COST CAUSATION MUST FOLLOW THE FULL ELECTRICAL CONSEQUENCE

printed heading · Topic match: Cost allocation

COST CAUSATION MUST FOLLOW THE FULL ELECTRICAL CONSEQUENCE Direct customer funding of interconnection facilities can be appropriate, but governance fails if review ends at the point of interconnection.
Read this passage Filed comments: Cost allocation

V. MATERIAL EVIDENTIARY CHALLENGES NEED INDEPENDENT ESCALATION

printed heading

MATERIAL EVIDENTIARY CHALLENGES NEED INDEPENDENT ESCALATION A stakeholder process cannot police itself when voting power, commercial interests, and institutional incentives are embedded in the same decision.
Read this passage

VI. THE SEPTEMBER DISPUTE-RESOLUTION PROCESS MUST END WITH

printed heading

THE SEPTEMBER DISPUTE-RESOLUTION PROCESS MUST END WITH DELIVERABLES The Commission's facilitated process should not conclude with generalized principles.
Read this passage

VII. CONCLUSION

printed heading · Topic match: Cost allocation

Persistence Analytics Group LLC respectfully requests that the Commission incorporate these accountability requirements into the next phase of Docket No.
Read this passage Filed comments: Cost allocation