PAG_Comments_ER26-3515-000
Text extracted from the eLibrary original (SHA-256 6064b724c8cd7a4e…). Download the original from the official source.
Contents · 8 sections
- I. INTRODUCTION
- II. THE LARGE LOAD REGISTRY SHOULD BE TREATED AS A DECISION-GRADE
- III. MATERIAL ASSUMPTIONS SHOULD HAVE IDENTIFIABLE REVALIDATION
- IV. IRAS RELIES ON OPERATIONAL CAPABILITY, SO CLAIMED LOAD REDUCTION
- V. BYONC SHOWS WHY REPORTED ARRANGEMENTS AND DURABLE CAPACITY
- VI. STATE COMMISSIONS AND ELECTRIC DISTRIBUTORS WILL NEED
- VII. THESE PRINCIPLES CAN IMPROVE RELIABILITY WITHOUT CREATING A NEW
- VIII. CONCLUSION
Read topic-matched comments in ER26-3515
Topics in the text: Registry access · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.Read this passage
I. INTRODUCTION
printed heading · Topic match: Registry access
Most significantly, PJM states that reliance on the registry must reflect accurate and complete information and that the registry is intended to become an accurate, complete, and reliable database supporting decisions about the amount of New Large Load available to provide IRAS.Read this passage Filed comments: Registry access
II. THE LARGE LOAD REGISTRY SHOULD BE TREATED AS A DECISION-GRADE
printed heading · Topic match: Registry access
THE LARGE LOAD REGISTRY SHOULD BE TREATED AS A DECISION-GRADE EVIDENTIARY RECORD, NOT ONLY A REPORTING REPOSITORY PJM proposes a registry with considerably more information than a conventional interconnection queue.Read this passage Filed comments: Registry access
III. MATERIAL ASSUMPTIONS SHOULD HAVE IDENTIFIABLE REVALIDATION
printed heading · Topic match: Registry access
MATERIAL ASSUMPTIONS SHOULD HAVE IDENTIFIABLE REVALIDATION TRIGGERS PJM expressly proposes that each Party promptly inform the Office of the Interconnection of any change in required registry information concerning a Large Load.Read this passage Filed comments: Registry access
IV. IRAS RELIES ON OPERATIONAL CAPABILITY, SO CLAIMED LOAD REDUCTION
printed heading · Topic match: Registry access
PAG does not suggest that every Large Load must be subjected to a single standardized physical test.Read this passage Filed comments: Registry access
V. BYONC SHOWS WHY REPORTED ARRANGEMENTS AND DURABLE CAPACITY
printed heading · Topic match: Registry access
BYONC SHOWS WHY REPORTED ARRANGEMENTS AND DURABLE CAPACITY SHOULD REMAIN DISTINCT PJM proposes BYONC as a pathway for New Large Loads to facilitate new capacity and reduce the quantity of load subject to IRAS.Read this passage Filed comments: Registry access
VI. STATE COMMISSIONS AND ELECTRIC DISTRIBUTORS WILL NEED
printed heading · Topic match: Registry access
Such provenance can be protected under the same confidentiality framework that PJM proposes for commercially sensitive information.Read this passage Filed comments: Registry access
VII. THESE PRINCIPLES CAN IMPROVE RELIABILITY WITHOUT CREATING A NEW
printed heading · Topic match: Registry access
The Commission need not require a new approval gate for every registry field.Read this passage Filed comments: Registry access
VIII. CONCLUSION
printed heading · Topic match: Registry access
CONCLUSION PAG supports PJM's effort to establish a Large Load Registry and an interim framework that better aligns large-load integration with resource adequacy and ratepayer protection.Read this passage Filed comments: Registry access
CERTIFICATE OF SERVICE
printed heading
If Persistence Analytics Group LLC has been added to the official service list before these comments are submitted, the undersigned will also serve the filing on all persons then appearing on that service list in accordance with Rule 2010 of the Commission's Rules of Practice and Procedure.Read this passage