Comments of Wolf Meridian Group re PJM Governance and Stakeholder Processes
Text extracted from the eLibrary original (SHA-256 e1d33ccb628c8054…). Download the original from the official source.
Contents · 10 sections
- I. Introduction and Summary
- II. Why Governance Speed Matters in a Large-Load Era
- III. Recommended Reform: A Permanent Critical-Issue Decision Track
- A. Objective Activation Criteria
- C. One Common Technical Record
- D. Formal State and Consumer Consultation Without Creating a Veto
- F. Mandatory Post-Implementation Review
- IV. Large Loads Demonstrate Why the Reform Is Necessary
- V. Relationship to the Commission's Questions
- VI. Conclusion
Read topic-matched comments in AD26-7
Topics in the text: Registry access · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Governance and Stakeholder Processes Docket No.Read this passage
I. Introduction and Summary
printed heading
Introduction and Summary Wolf Meridian Group respectfully submits these comments in response to the Commission's July 30, 2026 notice inviting post-technical-conference comments concerning PJM Interconnection, L.L.C. governance and stakeholder processes.Read this passage
II. Why Governance Speed Matters in a Large-Load Era
printed heading · Topic match: Reliability and curtailment
When assumptions affecting reliability, resource adequacy, transmission planning, market design, or customer costs change materially, PJM needs a process capable of separating verified information from projections, rapidly developing alternatives, obtaining state and stakeholder input, and reaching…Read this passage Filed comments: Reliability and curtailment
III. Recommended Reform: A Permanent Critical-Issue Decision Track
printed heading
Recommended Reform: A Permanent Critical-Issue Decision TrackRead this passage
A. Objective Activation Criteria
printed heading · Topic match: Registry access
A model schedule could include the following milestones: ●Day 0: Publish the issue charter, scope, decision authority, and schedule. ●By Day 15: Publish the common technical record and identify material data gaps. ●By Day 45: Publish a limited set of technically viable alternatives with…Read this passage Filed comments: Registry access
C. One Common Technical Record
printed heading
One Common Technical Record Expedited governance will only work if participants are debating policy choices from the same technical baseline.Read this passage
D. Formal State and Consumer Consultation Without Creating a Veto
printed heading · Topic match: Registry access
Formal State and Consumer Consultation Without Creating a Veto The Commission's agenda appropriately asks how states should participate in PJM's governance and stakeholder processes.Read this passage Filed comments: Registry access
F. Mandatory Post-Implementation Review
printed heading
Mandatory Post-Implementation Review Fast decisions are sometimes made with incomplete information.Read this passage
IV. Large Loads Demonstrate Why the Reform Is Necessary
printed heading
Large Loads Demonstrate Why the Reform Is Necessary Large-load growth provides a useful example of why governance structure and technical analysis can no longer be separated.Read this passage
V. Relationship to the Commission's Questions
printed heading
Relationship to the Commission's Questions The recommendations above directly respond to several questions posed in the July 23 technical conference agenda: ●Panel 1, Question 3 - Accountability and responsiveness: objective activation criteria, a fixed schedule, and a written Board disposition…Read this passage
VI. Conclusion
printed heading
The physical system is changing rapidly, and governance processes must be capable of responding to new information without sacrificing transparency or accountability.Read this passage