Motion to Intervene and Comments of Base Power Inc. re PJM Interconnection, L.L.C.’s 07/31/2026 filing
Text extracted from the eLibrary original (SHA-256 b738bb7354805123…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in ER26-3380
Topics in the text: Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
In these comments, Base requests two narrow drafting clarifications related to the peak shaving opt-out in proposed Tariff, Attachment DD, section 18.1(d).3 PJM’s clarification of these 1 18 C.F.R. §§ 385.211, 385.212, 385.214 (2026). 2 PJM Interconnection, L.L.C., Reliability Backstop Procurement…Read this passage Filed comments: Reliability and curtailment
I. MOTION TO INTERVENE
printed heading
Base respectfully requests that the Commission grant this motion to intervene with full party status, and reserves the right to file comments, protests, answers, and briefs in this proceeding.Read this passage
II. COMMENTS IN SUPPORT AND REQUESTS FOR CLARIFICATION
printed heading
COMMENTS IN SUPPORT AND REQUESTS FOR CLARIFICATION Base supports PJM’s RBP proposal and appreciates PJM’s positive engagement with stakeholders on the peak-shaving opt-out structure.Read this passage
A. PJM’s Peak-Shaving Opt-Out Recognizes and Gives Effect to Efforts By
printed heading · Topic match: Cost allocation
Coordinating these overlapping efforts will amplify their effectiveness, to the benefit of ratepayers.Read this passage Filed comments: Cost allocation
B. Base Requests PJM Make Two Narrow Clarifications on the RBP Proposal.
printed heading
Base Requests PJM Make Two Narrow Clarifications on the RBP Proposal.Read this passage
III. CONCLUSION
printed heading
CONCLUSION For the foregoing reasons, Base respectfully requests that the Commission grant its motion to intervene with full party status.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated: August 21, 2026 /s/ Qingliu (Mary) Yang Qingliu (Mary) Yang Juni PLLC 214-449-8699 mary@junienergy.comRead this passage