Motion to Intervene and Initial Comments of Amazon Energy LLC re PJM Interconnection, L.L.C.'s 07/31/2026 filing
Text extracted from the eLibrary original (SHA-256 cfc536598ac06c7c…). Download the original from the official source.
Contents · 8 sections
- I. INTRODUCTION
- II. COMMUNICATIONS
- III. COMMENTS
- A. Large-load customers that procured capacity before PJM submitted the RBP
- B. PJM’s cost-allocation proposal risks contravening longstanding cost-causation
- C. The Commission should direct PJM to provide an accelerated interconnection
- IV. MOTION FOR LEAVE TO INTERVENE OUT-OF-TIME
- V. CONCLUSION
Read topic-matched comments in ER26-3380
Topics in the text: Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No.Read this passage
I. INTRODUCTION
printed heading
ER26-3380-000 (filed July 31, 2026) (“PJM RBP Filing”). 2 PJM RBP Filing at 2 (emphasis in original). 2 federal authorities and avoids disrupting existing commercial arrangements.”3 While Amazon supports the objective of the RBP Proposal to ensure sufficient capacity is available to meet load…Read this passage
II. COMMUNICATIONS
printed heading
COMMUNICATIONS Communications should be addressed to the following person, who should also be designated for service on the Commission’s official service list for this proceeding: 3 Id. 3 William Friedman Amazon Energy LLC wfried@amazon.com Amazon requests, to the extent necessary, that the…Read this passage
III. COMMENTS
printed heading
III.Read this passage
A. Large-load customers that procured capacity before PJM submitted the RBP
printed heading
Under the RBP Proposal, large-load customers that do not procure their own capacity via bilateral contracts must pay capacity costs in the RBP backstop auction.Read this passage
B. PJM’s cost-allocation proposal risks contravening longstanding cost-causation
printed heading · Topic match: Cost allocation
Once the LSE load growth and capacity allocation calculation is performed, each zone’s/area’s resulting share of the Final RBP Target “shall remain constant throughout the fixed, fifteen-year term.” 5 PJM asserts that, under its proposed methodology, zones with new load not matched with new…Read this passage Filed comments: Cost allocation
C. The Commission should direct PJM to provide an accelerated interconnection
printed heading
The Commission should direct PJM to provide an accelerated interconnection process for RBP resources and resources committed to serve new large-load customers, so that new capacity comes online when the reliability needs arise.Read this passage
IV. MOTION FOR LEAVE TO INTERVENE OUT-OF-TIME
printed heading
MOTION FOR LEAVE TO INTERVENE OUT-OF-TIME Pursuant to Rules 212 and 214 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.212, 385.214, Amazon respectfully requests leave to intervene out-of-time in the captioned proceeding.Read this passage
V. CONCLUSION
printed heading
CONCLUSION WHEREFORE, for the foregoing reasons, Amazon respectfully requests that the Commission grant its motion to intervene out-of-time, permit Amazon to participate in this proceeding with full rights as a party to this proceeding, and consider the comments above and factor them into the…Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, DC, this 21st day of August 2026. /s/ William Friedman William Friedman Senior Corporate Counsel Amazon Energy LLC wfried@amazon.comRead this passage