ER26-3515-000 · 2026-09-02 · Individual No Affiliation

Supplemental Comments of Persistence Analytics Group LLC re the Interim Resource Adequacy Service proposed by PJM Interconnection, L.L.C

Text extracted from the eLibrary original (SHA-256 4e130c4c81107e8b…). Download the original from the official source.

Contents · 6 sections
  1. I. INTRODUCTION p. 1
  2. II. COMPENSATION ELIGIBILITY SHOULD FOLLOW DEMONSTRATED p. 2
  3. III. THE PERFORMANCE RECORD SHOULD SUPPORT THE FULL CHAIN p. 2
  4. IV. ELECTRIC DISTRIBUTORS AND RETAIL REGULATORS NEED p. 3
  5. V. MATERIAL CHANGES SHOULD TRIGGER REVALIDATION OF p. 4
  6. VI. CONCLUSION p. 5

Read topic-matched comments in ER26-3515

Topics in the text: Registry access · Reliability and curtailment · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.
Read this passage

I. INTRODUCTION

printed heading · Topic match: Registry access

INTRODUCTION Persistence Analytics Group LLC ("PAG") respectfully submits these limited supplemental comments concerning the Interim Resource Adequacy Service ("IRAS") proposed by PJM Interconnection, L.L.C. ("PJM").
Read this passage Filed comments: Registry access

II. COMPENSATION ELIGIBILITY SHOULD FOLLOW DEMONSTRATED

printed heading

COMPENSATION ELIGIBILITY SHOULD FOLLOW DEMONSTRATED PERFORMANCE, NOT MERELY DECLARED FLEXIBILITY IRAS necessarily depends on the ability of participating Large Loads to reduce consumption or otherwise respond when PJM requires relief.
Read this passage

III. THE PERFORMANCE RECORD SHOULD SUPPORT THE FULL CHAIN

printed heading

The Commission need not resolve each implementation detail in this proceeding.
Read this passage

IV. ELECTRIC DISTRIBUTORS AND RETAIL REGULATORS NEED

printed heading · Topic match: Registry access

The Large Load Registry and associated implementation processes should therefore preserve sufficient provenance to allow authorized users to distinguish among: represented capability; capability supported by implementation evidence; actual observed performance; and the quantity ultimately used for…
Read this passage Filed comments: Registry access

V. MATERIAL CHANGES SHOULD TRIGGER REVALIDATION OF

printed heading

MATERIAL CHANGES SHOULD TRIGGER REVALIDATION OF COMPENSATION-RELEVANT CAPABILITY PAG's August 13 comments recommended identifiable revalidation triggers for execution-critical assumptions.
Read this passage

VI. CONCLUSION

printed heading · Topic match: Retail and wholesale authority

PAG does not ask the Commission to resolve state retail jurisdiction, prescribe a universal performance test, or create a new approval layer.
Read this passage Filed comments: Retail and wholesale authority

CERTIFICATE OF SERVICE

printed heading

ER26-3515-000 in accordance with Rule 2010 of the Commission's Rules of Practice and Procedure.
Read this passage