ER26-3515-000 · 2026-09-03 · Public Service Commission of West Virginia

Comments of the Public Service Commission of West Virginia re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service

Text extracted from the eLibrary original (SHA-256 7f531628cae8ef1e…). Download the original from the official source.

Read topic-matched comments in ER26-3515

Topics in the text: Cost allocation · Retail and wholesale authority · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

It is that credit that the PSCWV opposes and requests that the Commission reject.
Read this passage Filed comments: Cost allocation

CONCLUSION

printed heading · Topic match: Cost allocation

CONCLUSION The State of West Virginia, the other states in PJM and the White House have similar public policies that NLL, mostly data centers, must not come at the expense of residential or commercial utility customers.
Read this passage Filed comments: Cost allocation

CERTIFICATE OF SERVICE

printed heading

Stewart, Associate General Counsel sstewart@psc.state.wv.us 201 Brooks Street, Post Office Box 812 Charleston, West Virginia 25323 (304) 340-0450 /s/ Susan M.
Read this passage