Protest of PJM Power Providers Group re the Interim Resource Adequacy Service
Text extracted from the eLibrary original (SHA-256 65a05304422b49ca…). Download the original from the official source.
Contents · 18 sections
- I. PROTEST
- A. The Federal Power Act Dictates Rejection of the IRAS Proposal
- B. PJM’s Proposal Would Inappropriately Stifle Supply from
- C. PJM Improperly Proposes to Degrade the Regional Reliability
- D. PJM Seeks to Add Unduly Discriminatory Requirements to its
- E. IRAS is too Indeterminate to be Found to be a Just and
- F. PJM Seeks to Use the Reliability Standards in a Way That FPA
- G. PJM’s Proposal is Inconsistent with NERC Reliability Standards
- H. The IRAS Proposal is Inconsistent with FPA Section 201 and
- II. COMMUNICATIONS
- III. CONCLUSION
- I. INTRODUCTION AND QUALIFICATIONS
- II. EXECUTIVE SUMMARY
- III. EFFECT ON RPM CLEARING PRICES AND THE RESOURCE-
- IV. PLANNING ON GROSS LOAD AND PROCUREMENT NET OF
- V. CONTINUING CAPACITY OBLIGATIONS AND COST
- VI. THE ABSENCE OF A BINDING SUBSTITUTE, AND THE
- VII. CONCLUSION
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Registry access · Retail and wholesale authority
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
The IRAS Proposal cannot and should not be approved in accordance with Section 205 of the Federal Power Act (“FPA”) as it is unjust, unreasonable and unduly discriminatory and preferential and will increase costs and undermine regional resource adequacy.4 For one, it explicitly is premised on the…Read this passage Filed comments: Reliability and curtailment
I. PROTEST
printed heading
I.Read this passage
A. The Federal Power Act Dictates Rejection of the IRAS Proposal
printed heading · Topic match: Reliability and curtailment
Cir. 1994) (“the Commission must be able to demonstrate that it has ‘made a 6 not to provide the evidentiary support of any economist or market-design witness.Read this passage Filed comments: Reliability and curtailment
B. PJM’s Proposal Would Inappropriately Stifle Supply from
printed heading · Topic match: Reliability and curtailment
Regardless, PJM also misses that while any individual $0/MW-Day offer requirement could be problematic for resource adequacy, the cumulative effect of $0/MW-Day offers from RMR resources, RBP resources (as PJM proposes in pending Docket No.Read this passage Filed comments: Reliability and curtailment
C. PJM Improperly Proposes to Degrade the Regional Reliability
printed heading · Topic match: Reliability and curtailment
PJM Improperly Proposes to Degrade the Regional Reliability Requirement PJM proposes to establish the IRAS quantity to reflect the regional capacity shortfall that it measures after the Third Incremental Auction pertaining to a Delivery Year has occurred. 54 In other words, PJM will reduce the…Read this passage Filed comments: Reliability and curtailment
D. PJM Seeks to Add Unduly Discriminatory Requirements to its
printed heading · Topic match: Reliability and curtailment
Yet loads added to the system before and after that date place the same demands on the system in terms of the capacity, energy and ancillary services and transmission service they require. Section 202(g) of the FPA explicitly provides that in the case of an energy or capacity shortage, all public…Read this passage Filed comments: Reliability and curtailment
E. IRAS is too Indeterminate to be Found to be a Just and
printed heading · Topic match: Reliability and curtailment
Cir. 1990) (the tariff must let purchasers “know in advance the consequences of the purchasing decisions they make”). 31 subject to a similar accreditation process and may be uncompensated, unduly discriminates against the latter.Read this passage Filed comments: Reliability and curtailment
F. PJM Seeks to Use the Reliability Standards in a Way That FPA
printed heading · Topic match: Reliability and curtailment
Therefore, a New Large Load that contracts for ten years of new capacity that must offer at $0/MW-Day obtains no assurance against curtailment and no guaranteed curtailment preference.Read this passage Filed comments: Reliability and curtailment
G. PJM’s Proposal is Inconsistent with NERC Reliability Standards
printed heading · Topic match: Reliability and curtailment
PJM’s Proposal is Inconsistent with NERC Reliability Standards it Relies Upon PJM seeks to define an Interim Resource Adequacy Service Action as “an Operating Instruction, as defined by NERC.”102 From there, it is able to mandate compliance because Reliability Standards IRO-001-4 R2 and TOP-001-6…Read this passage Filed comments: Reliability and curtailment
H. The IRAS Proposal is Inconsistent with FPA Section 201 and
printed heading · Topic match: Reliability and curtailment
FPA Section 201(b)(1) provides the Commission with jurisdiction over the sale of electric energy at wholesale in interstate commerce, and provides that such jurisdiction “shall not apply to any other sale of electric energy,” and further excludes from the Commission's jurisdiction “facilities used…Read this passage Filed comments: Reliability and curtailment
II. COMMUNICATIONS
printed heading
Rizzo Adam Masurovsky Arnold & Porter Kaye Scholer LLP 601 Massachusetts Avenue, NW Washington, DC 20001 (202) 942-5826 Sandra.Rizzo@arnoldporter.com Adam.Masurovsky@arnoldporter.com To the extent necessary, P3 respectfully requests a waiver of Commission Rule 203(b)(3), 18 C.F.R. § 385.203(b)(3),…Read this passage
III. CONCLUSION
printed heading · Topic match: Registry access
The overwhelming response to the recent Cycle One queue – over 220 GWs of new capacity – stands as a testament to the available supply poised to enter the market if durable market rules are upheld.119 However, to maintain reliability while new large loads are added to the grid, both new and…Read this passage Filed comments: Registry access
I. INTRODUCTION AND QUALIFICATIONS
printed heading · Topic match: Registry access
I have been retained by the PJM Power Providers Group to evaluate the capacity market consequences of the Interim Resource Adequacy Service (“IRAS”) and Large Load Registry proposed by PJM Interconnection, L.L.C.Read this passage Filed comments: Registry access
II. EXECUTIVE SUMMARY
printed heading · Topic match: Reliability and curtailment
These are not equivalent reliability measures, but their divergence shows that the procurement target no longer moves proportionately with the load PJM must plan to serve.Read this passage Filed comments: Reliability and curtailment
III. EFFECT ON RPM CLEARING PRICES AND THE RESOURCE-
printed heading · Topic match: Reliability and curtailment
Every new resource becomes an existing resource, and PJM must provide a sufficient and durable investment signal throughout the asset’s operating life.Read this passage Filed comments: Reliability and curtailment
IV. PLANNING ON GROSS LOAD AND PROCUREMENT NET OF
printed heading · Topic match: Reliability and curtailment
PJM’s stated ground was that Accredited UCAP values “may change as a result of factors that are not within the control of the resource owner, including changes in the expected patterns of resource adequacy risk on the system,” and that the must-offer requirement leaves a seller unable to hedge by…Read this passage Filed comments: Reliability and curtailment
V. CONTINUING CAPACITY OBLIGATIONS AND COST
printed heading
New Large Load should remain in PJM’s reliability studies because load that will be served must be reflected in the model and in the resulting planning parameters.Read this passage
VI. THE ABSENCE OF A BINDING SUBSTITUTE, AND THE
printed heading · Topic match: Reliability and curtailment
Section IV(b) separately determines how much Interim Resource Adequacy Service must be available, by comparing committed capacity to the PJM Region Reliability Requirement determined before the Third Incremental Auction, divided by the Pool-wide Accredited UCAP Factor.Read this passage Filed comments: Reliability and curtailment
VII. CONCLUSION
printed heading · Topic match: Reliability and curtailment
Attachment DD-4, section IV(b) governs the amount of Eligible New Large Load that must be available to provide Interim Resource Adequacy Service, determined after the Third Incremental Auction for each Delivery Year.Read this passage Filed comments: Reliability and curtailment
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 3rd day of September, 2026. _Hazel Lavarn-Walker_______ Hazel Lavarn-WalkerRead this passage